Comments of the
Upper Mississippi
River Basin Association
and
Governors Liaison
Committee
on the
Upper Mississippi
River-Illinois Waterway Navigation Feasibility Study
Memorandum for Record
regarding
“Ecosystem Restoration –
Discussion of
Authorities and Cost Sharing
Options,
Draft – Revised 25 June”
July 11, 2003
Successful implementation of the recommended plan resulting from the UMR-IWW navigation feasibility study will depend, in part, on resolving outstanding questions related to ecosystem restoration authorities and attendant cost sharing issues. Toward that end, the June 25, 2003 draft Memorandum for Record (MFR), developed by the Corps of Engineers, provides helpful background material on a range of potentially viable options. In particular, the states offer the following observations and perspectives:
Background (Section 2)
Section 2 of the MFR describes a number of existing Corps authorities related to UMR ecosystem restoration. While not necessary for the purpose of this MFR, it may ultimately be helpful to further describe how these authorities have been employed on the UMR and why they are insufficient. Currently, the MFR describes the accomplishments of the EMP, but has no similar documentation of the use of Section 1135, 206, or 204 authorities on the UMRS. If, in fact, as the states are inclined to agree, existing authorities are limited in their ability to address ecosystem restoration needs related to the ongoing cumulative effects of the navigation system, it will be important to clearly explain this constraint.
Section 2 concludes by stating that the feasibility report will “evaluate the Federal interest in recommending a plan adding ecosystem restoration as a project purpose….” The states believe this is a fundamentally important potential outcome of the study. The addition of ecosystem restoration as a project purpose would affirm what in many respects is the philosophical foundation, if not the operational reality, of how the system is currently managed. More importantly, the addition of ecosystem restoration as a project purpose will presumably have real and substantial effects on how the project is operated and maintained. Thus, the states are eager to further explore how such a dual project purpose might be structured and how it would affect operation of the existing project.
Mitigation of Navigation Improvement Impacts (Section 4)
In describing the types of impacts that will be mitigated, Section 4 of the MFR specifically mentions the impacts of increased traffic levels. In addition, the states assume that the site-specific impacts associated with construction of navigation improvements will be included in the mitigation package, even though those impacts are not explicitly noted in the MFR.
Section 4 concludes by stating that mitigation measures will be “implemented concurrently with the construction of navigation improvements.” Such an approach assumes that the impacts to be mitigated can be fully identified in advance. While the states strongly support concurrent mitigation, the potential need to mitigate for future traffic impacts, subsequent to completion of the construction of the navigation improvements, must also be recognized. The challenge will be to design an approach to mitigation that accommodates adaptive management, recognizing that many of the impacts may currently be unknown or may, in fact, be different than currently anticipated. Thus, the states have previously offered the concept of a mitigation trust fund for consideration. Whether or not such a trust fund is the most appropriate means for addressing this need, whatever approach is ultimately employed must ensure that sufficient authority and resources will be available to fully mitigate the project impacts subsequent to completion of construction.
Basic Cost Sharing
Options (Section 5)
Section 5 of the MFR
sets forth three basic approaches to defining cost sharing responsibilities
related to environmental restoration and enhancement and describes the policy and
statutory basis for each, with examples of their application. This section provides useful background
information and the states would simply observe that Option 5(b), “100 Percent
Federal as Addressing Ongoing Impacts of a Federally Constructed and Operated
and Maintained Project,” likely offers the most appropriate foundation for cost
sharing on the UMRS. For all the
reasons cited in the MFR, the UMRS is a river system with a major, and arguably
unique, federal presence.
While the states do
not believe that Option 5(c), based on Section 906(e) of WRDA 86, is a
promising option in the context of the navigation feasibility study, it is, in
fact, the current basis for EMP cost sharing.
The MFR correctly states that, for the EMP, the 100 percent federal
funding options in Section 906(e) have been limited to measures on land managed
as a federal refuge. However, it is
important to note that this limitation is a result of Administration policy and
is not embodied in law. As provided in
the EMP authorizing legislation, EMP habitat projects are to be cost shared in
accordance with Section 906(e). In
addition to projects on federal refuge lands, this would include projects that
benefit federally-listed threatened or endangered species, species of national economic
importance, species subject to international treaties, and anadromous fish.
Criteria for
Determining Cost Sharing (Section 6)
The criteria options
described in Section 6 offer distinctly different conceptual frameworks for
determining cost share responsibilities.
The states are pleased that, in addition to traditional criteria, the
MFR includes some options that reach beyond current practice and seek to frame
new approaches.
6(a): Measures attributable to on-going and cumulative existing project impacts = 100 percent federal
The states agree
with the theoretical foundation of this option (i.e., that measures to address
the ongoing and cumulative impacts of the navigation project should be 100
percent federally funded). However, as
the MFR notes, implementing this option would require an extraordinarily high
“degree of quantification and detailed accounting of cause and effect
relationships.” Investing in such
complicated and time-consuming analysis would not be prudent, particularly when
more simplified approaches are available and appropriate.
6(b): Measures involving modification of project structures and operations, and measures located on project lands or federal refuges = 100 percent federal
This option seeks to
simplify implementation of the premise that the federal government should bear
the cost of measures to address the ongoing and cumulative impacts of the
navigation project. In particular, the
simplifying assumption is that these impacts are largely within the “project
limits including Refuge lands.” The
practical value of such an assumption makes this option preferable to Option
6(a), despite the fact that a variety of definitional issues remain to be
resolved. In particular, clarification
of the term “project lands” will be necessary.
6(c): Measures involving modification of
structures and operations, measures on project lands and refuges lands, and measures in connected backwaters = 100 percent federal
This option appears to offer the most promise
and is the one the states are most interested in exploring further. Option 6(c) adds “measures in backwater
areas and side channels that are directly connected to the main channel
regardless of present ownership” to those measures already defined as fully
federally funded in Option 6(b).
Expanding the simplifying assumption from Option 6(b) in this way offers
a variety of advantages. As the MFR
notes, extending 100 percent federal funding to land acquisition in backwaters
and side channels directly connected to the main channel will help to address
the disparity in the amount of federal land between the upper and lower river
reaches. This disparity has been
particularly problematic for the EMP.
In addition, by broadening the 100 percent federal funding criteria to
include connected backwaters and side channels, Option 6(c) more closely
approximates the lands and waters affected by the navigation project, which is
the underlying premise of both Options 6(b) and 6(c). It also eliminates one of the major disadvantages of Option 6(b). Namely, implementation of large scale
measures like pool level management could become extremely complicated under
Option 6(b). For example, the costs of
lands and/or easements necessary to accommodate pool fluctuations resulting
from water level management would likely need to be apportioned among a large
number of nonfederal sponsors under Option 6(b). Presumably, this complicating factor will be at least partially
diminished by providing that projects involving connected backwater and side
channel areas be 100 percent federally funded.
With regard to measures that would be cost
shared 65-35, the MFR suggests that the program authorization be structured to
accommodate NGOs as nonfederal sponsors, credit for work-in-kind, and
carry-over of excess land value credits between projects. The states generally support these types of
provisions in cost shared programs and would be open to further discussion of
the details.
6(d):
Measures producing national benefits under Section 906(e) = 100 percent
federal
Given the Administration’s past reluctance to
fully use Section 906(e) as the basis for cost sharing in the EMP, it is
difficult to imagine that it would be useful to explore this option further in
the context of the navigation feasibility study. More importantly, this option is less attractive than the others
because it shifts the federal nexus from the navigation project to species and
land management definitions of federal interest. In so doing, this cost sharing option would also likely skew the
program toward species-based management, rather than the broader and more
appropriate objective of ecosystem sustainability.
While the above comments suggest that the
states view Option 6(c) as the most appropriate cost share criteria, the states
cannot guarantee that they will, in fact, be prepared to share in the costs of
any particular project or participate at any given level of programmatic
investment. The fiscal constraints
faced by the states, including restrictions on binding future legislatures,
preclude such commitments. Whether or
not states will be able to cost share, regardless of which cost share option is
ultimately recommended in the feasibility study, will depend on funding
availability, among other considerations.
This limitation will also be an important factor in the states’ ability
to take on the potential increased O&M costs associated with measures on
project lands managed under leasing arrangements.
Implementation Options (Section 7)
The states are not prepared to offer specific
comments about the array of implementation options presented in the MFR, until
the total package of recommended navigation and ecosystem restoration actions
becomes clear. However, the legislative
mechanisms used to authorize those actions will have a significant impact on
how and when they are implemented.
Recognizing that fact, the states offer the following general
observations:
EMP — The states will be better able to judge the most appropriate long-term
future role of the EMP when the full extent of ecosystem restoration
recommendations related to the feasibility study is defined. However, the states agree with the
assumption in the MFR that EMP “funding levels are not sufficient to meet the
restoration goals and objectives” and that simply expanding the EMP program
limits is not a viable option. The
existing EMP authority should be retained and fully utilized, basically in its
current form, for the near term.
Simple and Comprehensive — The states strongly urge that the vehicle
for implementing the actions recommended in the feasibility study be both
simple and comprehensive. Attempting to
pursue a variety of separate authorization strategies for different components
of the plan will diminish its integrity as a comprehensive and integrated
package and will likely unnecessarily complicate implementation.
Programmatic vs. Project-Specific
Authorizations — The merits
of authorizing some ecosystem restoration actions under a broad program
authority and others as specific projects need to be more fully explored. In particular, there may be important
considerations related to the total size (i.e., cost) of the proposed actions
that would suggest a need for separate authorizations. However, differences in the structures of
separate authorizations may create impediments to managing ecosystem
restoration in an integrated fashion, particularly if different measures and/or
actions require different cost sharing approaches, under different authorities.
Subsequent Authorizations — Seeking authorization of certain projects
at some future point in time, separate from authorization of other components
of the dual purpose integrated plan, diminishes the already fragile assurances
that all plan components will indeed be pursued in a balanced fashion. Admittedly, many of the large scale
ecosystem restoration projects, such as fish passage or pool level management,
will require more detailed planning than what is anticipated to be completed by
the conclusion of the navigation feasibility study. However, deferring the basic authorization to undertake such
projects could delay their implementation and weaken the relationship between
the navigation and ecosystem improvements inherent in recommendation of an
integrated plan.
Monitoring and Information Needs — None of the implementation options appear
to explicitly accommodate future monitoring and information needs related to
the adaptive management approach for implementing ecosystem restoration. Presumably, the recommended plan will
identify how these needs will be met, including, as necessary, either
enhancements to the LTRMP or other funding and authorization strategies. The states further assume that these data,
analysis, and research needs will be met at full federal cost.
Other Needs and Issues —The implementation options described in the
MFR are appropriately limited to actions directly within the study’s
scope. That includes, as defined in the
Interim Report, problems related to navigation traffic delays and environmental
problems associated with “changes to ecosystem structure and function imposed
by the operation and maintenance of the existing 9-Foot Channel Navigation
Project and potential navigation system improvements.” While this relatively narrow focus is
appropriate for the feasibility study, other national environmental issues,
such as invasive species, nutrients and Gulf Hypoxia, and floodplain management
are obviously related to environmental sustainability of the UMRS. Although the recommended plan is not
designed to address all these issues, implementation of the plan should take
advantage of opportunities to leverage the resources and programs of other
federal agencies including the Fish and Wildlife Service, U.S. Department of
Agriculture, and Environmental Protection Agency.