Minutes of the
Upper Mississippi River System
Environmental Management Program
Coordinating Committee
May 15, 2003
Spring Quarterly Meeting
Sheraton West Port Hotel
St. Louis, Missouri
Steve
Cobb of the U.S. Army Corps of Engineers called the meeting to order at 8:00
a.m. on Thursday, May 15, 2003. Other
EMP-CC members present were Charlie Wooley (USFWS), Scott Stuewe (IL DNR),
Kevin Szcodronski (IA DNR), Steve Johnson (MN DNR), Gary Christoff (MO DOC),
Gretchen Benjamin (WI DNR), and Leslie Holland-Bartels (USGS). A complete list of attendees follows
the minutes.
Minutes of the February Meeting
Scott Stuewe
moved and Gretchen Benjamin seconded a motion to approve the draft minutes of
the February 27, 2003 meeting as written.
The motion carried unanimously.
Program Management
Roger Perk
reported that, as of March 31, the EMP had expended $4.586 million since the
start of FY 03. This is 45 percent of
the program’s $10.15 million in scheduled expenditures for the year. Perk explained that the EMP has
approximately $3 million in additional funding needs for FY 03. The St. Paul District has transferred
approximately $300,000 to the St. Louis and Rock Island Districts to cover
short term contract obligations. In the
meanwhile, Perk is working with MVD and Headquarters in an effort to obtain the
additional funds. Steve Cobb said the
staff from Headquarters and the Divisions are scheduled to meet next week
concerning fiscal issues. Cobb said he
expects to have a sense of the EMP’s prospects for additional FY 03 funding
relatively soon.
HREP Funding Allocation Among Districts
Roger Perk said
the Corps is considering modifying the formula currently used to allocate HREP
funding among the districts for out-year planning purposes. The allocation would shift from MVP 35%, MVR
40%, and MVS 25% to MVP 30%, MVR 40%, and MVS 30%. Perk said that the Corps would like the EMP-CC to endorse this
change. Mike Thompson explained that
the current allocation limits the St. Louis District’s ability to plan
projects, a problem that will be exacerbated if funding levels increase. Perk and Thompson said the recommended
formula would more closely parallel the actual funding split among the
districts in recent years. Perk
explained that the actual annual allocation decisions will continue to be made
by Corps personnel based on program needs and in consultation with program
partners. He noted that recommendations
from the new HREP planning and sequencing process will be an important part of
the annual allocation decisions.
Steve Johnson
said that the Corps’ recommended change to the allocation formula for planning
purposes appears to be reasonable. He
noted that the existing formula is based on river miles, but that there are no
HREPs being pursued in the portion of the St. Paul District that is upstream of
the UMR Refuge. Moreover, Johnson
observed that the St. Louis District’s projects, while fewer in number, tend to
be substantially more expensive due to the nature of the river. Gretchen Benjamin said Wisconsin would be
comfortable with the change, as long as the allocation formula remains a
planning tool and the program retains the flexibility to make annual allocations
based on need and project merits. No
EMP-CC member expressed opposition to the Corps’ recommended change.
Report to Congress
Roger Perk
reported that work continues on the first three sections of the Report to
Congress. Perk said he delayed distribution
of these draft sections in order to allow time for further work. He said the draft material will be
distributed for partner review within the next few weeks.
According to
Perk, the August meeting will be devoted to resolution of any outstanding
issues, fine tuning the conclusions and recommendations, and discussion of the
first three draft RTC sections. He
estimated that additional chapters will be distributed for partner comment in
September or October. The schedule
calls for forwarding the draft report to MVD in January 2004.
LTRMP Funding Mechanism
Perk noted that
the LTRMP funding mechanism issue was not finally resolved at the February
EMP-CC meeting. At its November
meeting, the EMP-CC had dismissed all but one option from further
consideration. However, the committee
requested additional information concerning possible use of SF-1151 for funding
transfers from the Corps to USGS. MVR
and USGS staff have concluded that SF-1151 does not offer any advantages over
the current fund transfer method. More specifically, Perk noted that SF-1151
would not offer any cost savings and is more complicated. EMP-CC members concurred that this option
should not be pursued and that the RTC should not address the LTRMP funding
mechanism, given that there is no recommended action associated with the issue.
Delegated Authority for HREPs
Perk summarized
a new issue statement that the Corps prepared concerning delegated authority
for HREP approval. Currently, District
Commanders are authorized to approve HREPs under $1 million and the MVD
Commander may approve projects under $5 million. Approval authority remains at the Washington level for projects
over $5 million and for all projects that raise policy issues. Perk said the Corps program staff would like
to see delegated authority expanded.
More specifically, Corps staff recommend having HREP planning and design
approval occur at the District level for projects that cost less than $5
million and use relatively standard restoration practices. Authority to approve projects greater than
$5 million or incorporating untested practices or policies would reside at
MVD. Projects that influence nationwide
policy norms would be reviewed and approved at Headquarters. Perk estimated that this approach could
reduce project approval time by four to six months.
Steve Cobb
offered a modification to the issue paper, describing the provision for
Headquarters approval of certain projects as unnecessary. Instead, he said, all projects could be
approved at either the District or Division level. Cobb emphasized that, as a matter of standard practice, MVD would
consult with Washington on any projects raising major policy issues. He noted that his approach has been used in
other programs.
Gary Christoff
noted that all projects are approved at the District level under the Missouri
River Mitigation Program. He suggested
eliminating the proposed cost ceiling on the Districts’ approval authority,
reserving Division level approval only for those projects that raise policy
issues. Cobb cautioned against
recommending too much change for the EMP.
He noted that the recommendation he outlined would be in keeping with
the Continuing Authorities Programs.
Cobb said he was unfamiliar with the approval authorities under the
Missouri River Mitigation Program.
EMP-CC members
agreed that the RTC should recommend expanded delegated authority, as outlined
by Cobb—i.e., projects under $5 million that use standard practices approved at
the District level and all other projects approved by MVD, with the
understanding that MVD will consult as needed with Headquarters. Later in the EMP-CC meeting, the discussion
returned to the delegated authority issue.
Cobb suggested that there was no reason to wait for the RTC to pursue
this administrative change. He
indicated that MVD will advance the delegated authority recommendation prior to
completion of the RTC. It was agreed
that Corps staff would prepare information concerning the potential
implications of this change and that the RTC would describe the status of the
Division’s recommendation at the time the RTC is submitted.
Potential Conclusions and Recommendations
Perk explained
that MVR and UMRBA staff prepared a list of potential conclusions and
recommendations for the EMP RTC. He
emphasized that the list is based largely on input from previous RTC workshops
and EMP-CC meetings and is intended to catalyze discussion regarding major
ideas. Various EMP-CC members offered
the following specific suggestions concerning the list:
·
Eliminate
the reference to baseline funding in the conclusion regarding the challenges
associated with funding fluctuations, but retain a discussion of the value of
funding stability to the program.
·
Add a
conclusion stating that the EMP could effectively and efficiently utilize full
funding to meet program objectives.
Eliminate the recommendation concerning the program’s capabilities.
·
Modify the
conclusion statement regarding the EMP’s record of accomplishment to emphasize
the program’s significant contribution to the environmental sustainability of
the UMRS.
·
Use
language from the HNA report in the conclusion describing the assessment in
order to clearly communicate that the HNA is one of the tools used for HREP planning. Eliminate the term “iteration” in referring to the initial
HNA. “Version” was suggested as an
alternate term.
·
Several
questions were raised concerning the conclusion and recommendation related to
extending 100 percent federal funding to HREPs on all federally owned
lands. Among these questions were the
states’ willingness to operate and maintain projects on Corps lands, the
appropriateness of using EMP appropriations to build projects that reasonably
fall within Park Service and Forest Service missions, the potential perception
that expanding 100 percent federal projects represents a diminution of the
states’ commitment to the EMP, the extent of UMR land holdings by other federal
agencies, and the relationship between such a recommendation in the RTC and the
Navigation Study’s potential restoration recommendations. It was agreed that Corps staff would further
explore the potential for recommending such an expansion as part of the
RTC. This will include coordinating
within the Corps, communicating with other potentially affected federal
agencies, and assembling information on the potential number and types of
projects under such an approach.
·
Modify the
conclusion concerning the Fish and Wildlife Service’s O&M capacity to
clarify that the issue is the Service’s ability to fund O&M of HREPs on its refuges.
·
Modify the
conclusion regarding the LTRMP’s status among monitoring programs to describe
it as “one of the most consistent,
comprehensive….”
·
Consider
adding a conclusion focusing on the importance of analysis work within the LTRMP. Leslie Holland-Bartels agreed to draft such
a conclusion for the committee’s consideration. It was agreed that the RTC should not recommend increased funding
for analysis, given that the partnership has always had the option of
allocating more funding toward this work and has elected not to do so.
·
Develop
specific legislative language to accompany the RTC recommendation to permit
NGOs as cost-share partners for HREPs.
· As needed, rework the conclusion and
recommendation concerning delegated authority to reflect the status of the
issue at the time the RTC is submitted.
MVD will be recommending additional delegated authority for the
Districts and the Division in advance of the RTC.
Perk asked
EMP-CC members to provide him with any more detailed, written comments
concerning the potential conclusions and recommendations by June 13. He explained that he would use those
comments as well as today’s discussion to prepare a revised version of the RTC
conclusions and recommendations for the partners’ review by mid-July.
At this point in
the meeting, Steve Cobb departed.
Charlie Wooley chaired the remainder of the meeting.
Long Term Resource
Monitoring Program
Overview of FY 03 Analysis
Effort
Leslie
Holland-Bartels noted that the FY 03 analysis effort was initiated in
anticipation of continued funding reductions.
However, she emphasized that the analyses are providing information
needed to inform decisions about program priorities under either increasing or
decreasing funding scenarios. The
equivalent of 24 staff years is being devoted to the FY 03 analysis. Holland-Bartels offered a brief summary of
the results so far, while encouraging EMP-CC members and others to contact
field station leaders and discipline specialists directly for more detailed information
concerning any of the analyses.
Based on the
results so far, Holland-Bartels said there appears to be potential for
additional monitoring refinements that would increase efficiency. At the same time, however, it may be that
there are some elements of current monitoring that should be expanded. Overall, Holland-Bartels said the results of
the FY 03 analyses confirm the soundness of previous refinements to the
monitoring program. Even if program
resources were to increase substantially, USGS would not favor revisiting those
decisions. However, she said further
analyses are required before USGS would be prepared to consider any additional
refinements. Holland-Bartels described
some of the nuances between data from different pools. For instance, while there is certainly some
clustering in vegetation data on the upper pools, there are also distinct
differences, with Pools 4, 5, and 8 having a fair amount of commonality, and
Pools 7, 12, 11, and 13 each appearing to be rather distinct. Holland-Bartels said USGS would be reluctant
to reduce the monitoring program’s spatial coverage unless fiscal constraints
demand such an approach.
Among the
potential monitoring refinements under evaluation, USGS and Missouri DOC are
looking at reducing the Open River field station’s water quality monitoring
effort and substituting data from USGS’s nearby National Stream Quality
Accounting Network (NASQAN) station.
Preliminary analyses show strong correlations between the data from the
LTRMP monitoring and the NASQAN station.
The two agencies are also attempting to develop a better metric of
invertebrate health for use on the Open River. The current protocol in not well
suited for the Open River, where it yields many samples with no invertebrates.
FY 04 Work Planning
Holland-Bartels
explained that USGS has implemented a process for gathering input regarding the
future LTRMP, in anticipation of increased resources in FY 04. She distributed handouts describing the
process. Ad hoc teams will focus on specific areas previously identified as
priorities, including LTRMP analyses and science planning. Staff will also be available to help develop
problem statements regarding other topics or issues that people want to raise
for discussion. In addition, USGS has
issued a call for more focused and detailed project pre-proposals. These pre-proposals are to be submitted
through specified points of contact.
Holland-Bartels expressed optimism that this more structured approach
will be helpful in organizing input regarding the FY 04 program. She noted that this approach will put
responsibility on technical staff to fully scope a potential work item and
detail its anticipated contributions.
Highlights from the FY 03 Analyses
According to Holland-Bartels,
the analysis work and development of the individual component reports is all on
schedule. She briefly described some of
the highlights from the ongoing efforts:
· Outpool sampling shows fisheries data
from Pool 3 and Upper Pool 4 tend to cluster with data from Pools 19 and 20,
with a predominance of emerald shiner in all of these areas. The explanation for this is unclear. One hypothesis is that the similarity in
fish communities is a legacy of industrial pollutants in these pools.
·
LTRMP
analysis has revealed a relationship between water level fluctuation and
submersed aquatic vegetation (SAV).
Fluctuations of more than 0.5 meters appear to inhibit SAV, raising
obvious questions about the potential benefits of managing the system to reduce
such fluctuations. This analysis
employed existing aerial photography in a new way.
·
Outpool
sampling has proven to be a valuable reconnaissance tool, but is not helpful in
determining the reasons for what is observed.
USGS recommends retaining outpool sampling as a tool, while looking for
other methods to gain insight into the portions of the system that are not
covered by trend pool monitoring.
·
For most
years, LTRMP data reveal a negative correlation between SAV abundance and
turbidity levels. However, this was not
the case in 2000, a year characterized by rapid, storm-driven spikes in
turbidity that were relatively short in duration. This observation suggests the hypothesis that plants may be able
to withstand elevated turbidity as long as it is brief.
·
Comparison
of wild celery modeling results with aerial photography data shows the model to
be a relatively good predictor of actual vegetation patterns.
·
Stratified
random sampling has allowed the LTRMP to detect changes resulting from
HREPs. For example, vegetation
monitoring detected a positive response in SAV to island construction in Pool
8.
·
Monitoring
revealed a dramatic shift in fish community structure in 1994. Specifically, there was a significant influx
of juvenile fish produced during the 1993 flood. However, the duration of this effect appears to be somewhat
species-dependent. The “benefit” of the
flood was relatively short-lived for bluegill, somewhat longer lasting for
largemouth bass, and even more enduring for carp.
·
The water
quality effects of tributary inflows are extensive and persistent. This is a phenomenon that would not have
been captured without the shift to stratified random sampling within trend
pools.
·
LTRMP data
would appear to suggest that there is a trend toward autumn nitrogen
application. However, longer term
hydrologic data suggest that this pattern may be related to discharge, rather
than to changes in application practices.
LTRMP staff are further evaluating the relevant data, including data
from USGS NASQAN stations.
·
Over 66
percent of the sites found to have zebra mussels were in the lower third of the
pools sampled. This is not particularly
surprising, given the zebra mussel’s life cycle, but it may have implications
for water management (i.e., is there a way to reduce settling of veligers?) and
for mussel relocation efforts.
· LTRMP macroinvertebrate data, combined
with Fish and Wildlife waterfowl data, shows a correlation between fingernail
clams populations and diving duck numbers.
Data Access
Holland-Bartels
reported that efforts to improve access to data and insights from the LTRMP are
continuing in FY 03. A newly developed
web browser for the fish data allows users to access current as well as
historical data, develop their own queries, and download and print
results. It is possible that similar
browsers could be developed for the other LTRMP data. LTRMP staff are also developing a master database of life history
characteristics for fish that will include more than 130 parameters. Holland-Bartels said this is a major effort,
but emphasized that it should be a very useful tool for habitat analysis. Staff are also developing a field guide to
exotic fish species found in the UMRS.
A-Team Report
Tom Boland
reported that the A-Team’s April 23 meeting included a presentation on the
analysis results. Boland said results
support the A-Team members’ belief that the core program is producing good
information. He emphasized the importance
of collecting annual data, warning that important events and changes can occur
quickly. Boland called for an approach
that allows the program both to collect and analyze information continuously,
rather than reducing monitoring efforts periodically to allow data to be
analyzed.
Boland briefly
described the A-Team’s discussions at its meeting, noting that several members
cautioned against making too many changes in the pursuit of efficiency. There is particular concern that too many
changes could risk the comparability of the LTRMP data over time. However, members also recognized the need to
retain flexibility in the program.
Boland said the A-Team’s July 23 meeting will focus on the LTRMP’s FY 04
work plan. He expressed optimism
regarding the program’s potential under increased funding.
Charlie Wooley
asked about the LTRMP’s ability to track ruffe, if this exotic fish moves from
the Great Lakes to the UMRS. Boland
said the LTRMP would not capture such an event with its baseline monitoring
program, noting that none of the trend pools is near the Chicago areas. Boland emphasized that the threats posed by
exotics illustrate why the LTRMP needs sufficient resources to permit targeted
monitoring in addition to the baseline effort.
Gretchen
Benjamin asked about the relationship between the USGS’s Science Planning
Process and the call for FY 04 proposals.
Boland said he was not sure of the relationship, and stressed the
importance of not going back every few years and reinventing the program. He expressed concern with the states’
capacity to participate in the ad hoc
teams. Marvin Hubbell said that
development of the FY 04 scopes of work and the Science Planning Process will
proceed on parallel paths. He expressed
confidence that there will be an opportunity to coordinate between the two
efforts prior to implementation of the FY 04 work plan. Benjamin questioned whether the two efforts
might be redundant. Chuck Theiling said
the process of clearly establishing the program’s research objectives should
prove helpful.
Dick Steinbach said
he has appreciated Boland’s leadership of the A-Team during difficult times for
the LTRMP. Boland announced that John
Sullivan will become the next A-Team chair.
This change will take place sometime in the fall or winter.
Roger Perk
announced that Marvin Hubbell, formerly with Illinois DNR, has joined the Rock
Island District as the Corps’ new LTRMP coordinator.
HREP Planning and Sequencing
Roger Perk
described the new draft HREP Planning and Sequencing Framework, explaining that
he revised the May 2000 draft based on partner comments and interim
developments, such as the pool planning efforts. Perk emphasized that ecological merits will remain the most
important consideration under the new process.
As with the May 2000 version, the revised framework is designed to
provide structure for HREP planning while retaining the flexibility needed for
the program to be effective.
Perk reviewed
the basic goals of the process, which include ensuring that HREPs address UMRS
ecological needs at multiple scales, enhancing public understanding of project
planning and selection, and retaining program flexibility. The framework provides for a four stage
process after development of project fact sheets. Perk stressed that the Stage 1 District Ecological Evaluation
will be based on existing information.
While the new fact sheet format is more detailed than the previous
version, people developing a project proposal will only be asked to complete
those portions for which information is available. In response to a question from Jon Duyvejonck, Perk said he
anticipates that completed fact sheets will typically be from two to five pages
in length.
Perk said he
would like to keep the size of the Stage II System Ecological Team (SET) to
approximately four to six people, if possible.
Perk said he anticipates that the SET will be comprised of experts from
this region. Gretchen Benjamin asked
what, specifically, the SET will be reviewing.
Perk said the SET will review the top projects from each District
Ecological Team (DET), considering the project fact sheets as well as the DETs’
comments and recommendations. He
emphasized that there will be two-way communication between the SET and the
DETs. If the SET has questions or
concerns with a project, it can ask the DET for additional information or
suggest refinements to the project.
Perk explained that the MVD Commander will appoint the SET members, with
advice from the EMP-CC. He asked Committee
members to provide him with names of potential SET candidates prior to the
August EMP-CC meeting.
Perk asked the
EMP-CC members whether they would like all Committee members to participate on
the Stage III Program Planning Team, or whether they would like to name some
representatives to the Team. Gary
Christoff suggested that having a subset of the EMP-CC on the Program Planning
Team would be sufficient. Steve Johnson
expressed reservations about such an approach, suggesting instead that all
EMP-CC members should be on the Team.
He proposed that the Team do its work as part of the EMP-CC’s regularly
scheduled meetings in the interest of efficiency.
Perk requested
comments on the revised HREP Planning and Sequencing Framework by June 13. Based on those comments as well as today’s
discussion, Perk will revise the framework, consulting as needed with the
program partners, and present a proposed final framework in time for action at
the EMP-CC’s August 7 meeting. Don
Powell is in the process of developing a flowchart depicting the process. Perk said he would provide this flowchart to
the EMP-CC prior to the June 13 comment deadline.
Dick Steinbach
expressed concern that the HREP framework is attempting to fix a nonexistent
problem. He voiced particular
reservations about the Stage II System Ecological Evaluation, cautioning that
it could impede progress toward program goals.
Steinbach said he anticipates that small, targeted projects will not
fare well under the new process.
Instead, he said the process will reward a “Christmas tree” approach
toward developing projects that are designed to compete well, rather than to
meet pressing ecological needs. Perk
said the SET will be told that they should be looking for projects that address
real needs and that small projects should not be precluded from priority. Perk stressed the importance of maintaining
a good dialog between the SET and the DETs.
Don Powell
encouraged the states to consider how the River Resources Forum (RRF) will
relate to this new process, which appears to give the Fish and Wildlife Work
Group (FWWG) new authorities that the RRF has not previously granted it. Barb Naramore recalled that this was a topic
of considerable discussion during development of the May 2000 framework. Those involved concluded that that new
process should not alter the relationship between the FWWG and the RRF, or
between the Rock Island District’s Fish and Wildlife Interagency Committee,
which will serve as MVR’s DET, and its governing River Resources Coordinating
Team. Specific language to that effect
was included in the May 2000 framework, and is retained in the revised
draft. Steve Johnson emphasized that
the FWWG is a committee of the RRF and that this relationship needs to
remain. He suggested that the flowchart
make this relationship clear.
Joyce Collins
noted that the framework calls for annual System Ecological Evaluations and
asked whether the district evaluations would also be done annually. She suggested that annual evaluations might
be too frequent and recommended modifying the framework to call for evaluations
every two years, or on an as needed basis.
Perk said that, as an initial approach, annual evaluations seemed
appropriate, in part to reduce the pressure at the district level to identify
every possible project during the first round.
He noted that there will be opportunities to modify the process as
needed, based on experience.
Kevin
Szcodronski expressed his appreciation of Perk’s efforts in revising the
framework. Szcodronski said he thinks
the new draft strikes a good balance between providing structure and retaining
flexibility. He urged the program
partners to implement the new process and learn from experience, rather than
trying to perfect it in the abstract before applying it. Szcodronski expressed his hope that future
EMP program managers will exhibit the same flexibility as Perk.
Other Business
Barb Naramore
announced that the upcoming quarterly meeting schedule includes meetings on
August 5-7, 2003 in the Twin Cities and November 18-20, 2003 in La Crosse. The winter quarterly meetings are tentatively
scheduled for February 24-26, 2004 in St. Louis, but the dates and location
have not yet been finalized. EMP-CC
business meetings will take place on the third day of each meeting cycle.
Kevin
Szcodronski announced that he has accepted a new position as Chief of Iowa
DNR’s Parks Bureau. As a result, he
will be transitioning out of his duties on the Mississippi and Missouri
Rivers. Szcodronski said he did not yet
know exactly how or when these duties would be filled, but said the transition
process would likely take place over several months.
With no further
business, the meeting adjourned at 11:50 a.m.
EMP-CC
Attendance List
May 15, 2003
|
Steve Cobb |
U.S. Army
Corps of Engineers, MVD |
|
Charlie Wooley |
U.S. Fish and Wildlife
Service, Region 3 |
|
Leslie
Holland-Bartels |
U.S.
Geological Survey, UMESC |
|
Scott Stuewe |
Illinois
Department of Natural Resources |
|
Kevin
Szcodronski |
Iowa
Department of Natural Resources |
|
Steve Johnson |
Minnesota Department
of Natural Resources |
|
Gary Christoff |
Missouri
Department of Conservation |
|
Gretchen
Benjamin |
Wisconsin
Department of Natural Resources |
|
Rich
Worthington |
U.S. Army
Corps of Engineers, Headquarters |
|
Don Powell |
U.S. Army Corps
of Engineers, MVP |
|
Roger Perk |
U.S. Army
Corps of Engineers, MVR |
|
Marvin Hubbell |
U.S. Army
Corps of Engineers, MVR |
|
Chuck Theiling |
U.S. Army
Corps of Engineers, MVR |
|
Mike Thompson |
U.S. Army
Corps of Engineers, MVS |
|
Brian Markert |
U.S. Army
Corps of Engineers, MVS |
|
Eric Laux |
U.S. Army
Corps of Engineers, MVS |
|
Kathy
Kornberger |
U.S. Army
Corps of Engineers, MVS |
|
Tim Yager |
U.S. Fish and
Wildlife Service, Region 3 |
|
Jon Duyvejonck |
U.S. Fish and Wildlife
Service, Rock Island Field Office |
|
Joyce Collins |
U.S. Fish and
Wildlife Service |
|
Tom Boland |
Iowa
Department of Natural Resources |
|
Janet
Sternburg |
Missouri
Department of Conservation |
|
Mike Wells |
Missouri Department
of Natural Resources |
|
Gary Wooten |
Natural
Resources Conservation Service, Midwest Region |
|
Bill Franz |
U.S.
Environmental Protection Agency, Region 5 |
|
Larry Shepard |
U.S.
Environmental Protection Agency, Region 7 |
|
Holly Stoerker |
Upper
Mississippi River Basin Association |
|
Barb Naramore |
Upper
Mississippi River Basin Association |