Minutes of the
Upper
Mississippi River System
Environmental
Management Program
Coordinating
Committee
May 18, 2000
Spring
Quarterly Meeting
Marriott
Madison West
Madison,
Wisconsin
Dusty
Rhodes of the U.S. Army Corps of Engineers called the meeting to order at 8:07
a.m. on Thursday, May 18, 2000. Other
EMP-CC members present were John Blankenship (USFWS), Leslie Holland-Bartels
(USGS), Marvin Hubbell (IL DNR), Kevin Szcodronski (IA DNR), Steve Johnson (MN
DNR), Gordon Farabee (MO DOC), and Terry Moe (WI DNR). A complete list of attendees is
attached.
Minutes of the February
Meeting
Terry
Moe moved and Kevin Szcodronski seconded a motion to approve the minutes of the
February 17, 2000 EMP-CC meeting as written.
The motion carried unanimously.
Program Management
FY 00 Fiscal Performance
Leo
Foley reported that the EMP's expenditures through March 31 totaled $5.257
million. This represents approximately
29 percent of the $18.438 million in total expenditures scheduled for the year. HREP expenditures through March totaled
$2.708 million, compared with scheduled expenditures for the year of $11.567
million. LTRMP expenditures were $2.466
million, compared with annual scheduled expenditures of $6.748 million. Obligations through the end of March totaled
$5.210 million for HREPs and $6.547 million for LTRMP. Foley cautioned that the expenditure figures
are a bit low for this point in the year, but expressed optimism that the
program will achieve full expenditures for the year. He noted that there is a contingency plan to transfer money from
HREPs to the LTRMP if project delays threaten the habitat program's ability to
expend fully.
Terry
Moe asked about the recission of $357,000 reported on the spreadsheet. Foley said this was the EMP's proportional
cut of a Corps-wide recission. He
explained that this amount was subsequently reprogrammed back to the EMP from
funds available within the Rock Island District.
Moe
asked whether the EMP still includes a recreation projects authority. Foley said he believes the recreation
projects authorization has expired, but said he would request a legal opinion
on the matter. Rhodes noted that the
Corps can construct individually authorized recreation projects with a 50 percent
nonfederal cost share.
In
response to a question from Gordon Farabee, Foley explained that project
planning starts will generally await the new HREP prioritization process. However, the districts have been instructed
not to await the prioritization process if they need to initiate planning on
new HREPs in order to keep projects in the pipeline. Foley said this will be done only to the extent necessary to
avoid gaps in the flow of projects.
Moe
asked about the regional administration line item on the spreadsheet. Foley said this reflects costs for overall
project management, including the project manager's time. He explained that these expenses were
previously identified as division coordination costs on the spreadsheet.
FY 01 Funding Outlook
Foley
reviewed the likely funding allocations within the EMP under three different
funding scenarios:
|
|
FY-01 Budget Proposal |
FY-01 Budget Proposal |
FY-01 Budget Proposal |
|
|
|
|
|
Total $ Budgeted |
18,000 |
22,500 |
25,000 |
|
|
|
|
|
|
S&S (10.0%) |
1,800 |
2,250 |
2,500 |
|
Administrative Costs |
110 |
110 |
110 |
|
HNA |
- |
- |
- |
|
|
|
|
|
|
Sub (Tot-Admin) |
16,090 |
20,140 |
22,390 |
|
|
|
|
|
|
LTRMP 31.4% |
5,052 |
6,324 |
7,030 |
|
|
|
|
|
|
HREP (68.6%) |
11,038 |
13,816 |
15,360 |
|
St. Paul District (35%*) |
3,863 |
4,836 |
5,376 |
|
Rock Island District (40%*) |
4,415 |
5,526 |
6,144 |
|
St. Louis District (25%*) |
2,759 |
3,454 |
3,840 |
|
|
|
|
|
|
* HREP allocation could
change based on the project prioritization process |
|||
|
|
|||
Foley
noted that the scenarios correspond with the President's budget request ($18.0
million), the amount advocated by the UMR Congressional Task Force ($25.0
million), and a possible mid-range compromise amount ($22.5 million). He emphasized that the Corps does not yet
have any strong indication as to what the FY 01 appropriation will be.
Implementation Guidance
Foley
reported that Corps headquarters issued its EMP implementation guidance to MVD
on May 12. The guidance addresses
provisions of WRDA 99 as well as recommendations contained in the Partnership
Report to Congress. Foley noted that
the guidance is largely consistent with the recommendations that MVD had
previously submitted to headquarters, including credit for in-kind services,
confirmation of land acquisition authority, and increased delegation of
authority. General Anderson has not yet
officially transmitted the guidance to the Rock Island District with directives
regarding its implementation.
Holly
Stoerker asked about the provision requiring the Assistant Secretary of the
Army’s (ASA) approval of in-kind services prior to the execution of the
work. Foley explained that cost sharing
agreements require ASA approval, though this authority is frequently
delegated. Consistent with this general
policy, the EMP guidance is requiring specification of in-kind services in the
project cooperation agreement (PCA). He
said project sponsors wishing to obtain credit for work early in a project
would have to sign a PCA prior to initiation of the definite project report. Marvin Hubbell asked whether is might be
possible to have 2 PCAs, one for the project planning phase and the other for
construction. Foley said this approach
has been used in other programs and could be applied to EMP projects. Dusty Rhodes expressed confidence that the
requirement for advance approval of in-kind services will not be onerous,
regardless of whether the ASA delegates approval authority. Rhodes encourages those with questions about
the PCA process to contact Mike Hardin at MVD.
Hubbell
said he is quite pleased with the overall implementation guidance, noting that
its land acquisition provisions will be particularly helpful. Jeff Stein observed that the guidance
directs MVD to prepare a proposal to implement the independent technical
advisory committee. Stein asked about
MVD's timeframe for developing this proposal.
Rhodes said MVD is still reviewing headquarters' guidance. Upon completion of this review, General
Anderson will issue directives regarding specific actions to implement the
guidance.
Partnership Issues
Holly
Stoerker reported that the directors of the five state EMP partner agencies
will be sending joint letters to the Fish and Wildlife Service and the Corps of
Engineers. She explained that the
letters are in follow-up to discussions at the February 2000 EMP-CC
meeting. According to Stoerker, the
letters will convey the states' perspectives on the future of the EMP's HREP
component. In particular, the letter to
General Anderson will focus on the states' ability and willingness to cost
share and will also urge the Corps to seek increased funding for the EMP and
express the states' desire for DOI to fund the Service's involvement. The letter to Director Hartwig will
emphasize the importance of all program partners contributing to the program,
express the states' willingness to help Region 3 obtain the resources it needs
from within the Interior budget, and ask how the states should work with the
Service on particular projects given the budget constraints.
John
Blankenship said the states' letter does not come as a surprise. He noted that the UMR Congressional Task
Force supports allocating an additional $6 million to address Region 3's
needs on the UMR. Blankenship said this
amount would meet needs in several areas, including the EMP, but said he is not
optimistic that Region 3 will actually receive this amount. He noted that there are projects for both
UMR refuges within the Service's Refuge Operating Needs (RONs) proposal, but
said the EMP is competing with other pressing needs even within the UMR
refuges, including comprehensive refuge planning and requirements under the
Refuge System Administration Act.
Reiterating his comments from the February meeting, Blankenship assured
the EMP partners that the Service will meet its existing commitments to habitat
projects. However, he emphasized that
the Service's ability to take on additional obligations, given Region 3's
resource constraints, is in question.
Marvin
Hubbell said he has alerted Illinois DNR field staff that the Service's HREP
planning and O&M constraints may affect work with Service staff on
individual habitat projects. Hubbell
requested guidance from Blankenship on the states' options for working with the
Service in light of these constraints.
Blankenship said the Service will respond promptly to the states' letter. He suggested that it be addressed to Service
Director Rappaport Clark rather than Regional Director Hartwig. In response to a question from Stoerker, he
acknowledged that this strategy would likely delay the Service's response.
Regarding
the states' letter to the Corps, Dusty Rhodes said he believes the Corps has
been aggressive in budgeting for the EMP.
He emphasized that the Corps can only seek money for the HREP program to
the extent that there are project sponsors available. Moreover, he stressed that the Corps will not design projects
that are inappropriately loaded with first construction costs in an effort to
reduce future O&M costs. Rhodes
recommended that the states include the ASA and the Office of Management and
Budget among the addressees in their letter to the Corps.
Kevin
Szcodronski recommended that the states change the addressees of the joint
letters as suggested by Blankenship and Rhodes. The other state EMP-CC members concurred.
Blankenship
expressed cautious optimism that the Service will see an increase in refuge
O&M funding. According to
Blankenship, the prospects are not as good for increased DOI funding for
project planning. He explained that the
Service's request to the Corps for $300,000 in planning money would support one
staff person on each of the two UMR refuges.
These staff people would be totally dedicated to the EMP. In addition, the funding would also cover
some of the time from ecological services and fisheries staff who are also
involved in HREP planning.
Greg
Ruff noted that Region 3's January 27 letter raised the following three issues:
1)
transfer
of EMP funds to support the Service's HREP planning role,
2)
assistance
with rehabilitation of damaged or defective projects after project transfer,
and
3)
O&M
funding.
Ruff
reported that MVD is inclined to transfer EMP funds to the Service for HREP
planning. He explained that the Corps
understands the need for Service involvement in the preparation of items such
as Fish and Wildlife Coordination Act Reports (CARs), and typically funds such
work by the Service for other Corps projects.
He said the Corps does not have authority to transfer funds to address
either of the other two issues raised by the Service. Rhodes elaborated on how the Corps works with the Service on
other projects. He emphasized that the
Corps pays the Service to provide specific products that are needed, such as
CARs, but does not transfer money to support permanent staff. Rhodes said any transfers of EMP funds would
follow this practice.
Szcodronski
asked about the specific work that would be performed by the two refuge staff
dedicated to the EMP. Blankenship
emphasized that the Service is involved throughout the entire HREP planning
process, not merely in the preparation of CARs. This includes a range of activities during a project’s early
stages. He said this is also true of
the Service's involvement in other Corps projects. Szcodronski noted that Iowa is contemplating several projects
that are at least partly on refuge lands and said the state has typically
worked with the individual site managers on such projects. Blankenship said the EMP-dedicated refuge
person would serve as the point of contact for all projects on his/her refuge. He observed that refuge staff with other
responsibilities are simply too busy to dedicate sufficient time to HREP
planning. In response to a question
from Szcodronski, Blankenship said staff from the Rock Island and Twin Cities
field offices and the La Crosse fisheries office also work on HREPs and need
funding to support their involvement.
Rhodes emphasized that the Corps will buy products, not staff time. As such, the Corps will require scopes of
work (SOWs) that identify specific deliverables, but will not concern itself
with who does the work or where it is performed.
Szcodronski
said he understands Rhodes' point, but stressed that he and the other states
would like to have an idea how the money will actually be spent. Gordon Farabee asked whether the states will
have an opportunity to provide input on the SOWs. Rhodes said the Corps is willing to have the states review the
scopes, but stressed that this review must be timely and efficient.
Terry
Moe voiced strong opposition to the Corps' anticipated course of action. He said paying the Service for specific
products amounts to paying them to perform the same work that the states do for
free. Blankenship said the Service
simply does not have the funds to make future EMP work a priority. Szcodronski noted that the Service has also
expressed concern with its ability to meet O&M obligations for additional
projects. He observed that there is no
point in transferring money to the Service to plan projects if it cannot
operate and maintain those projects.
Blankenship expressed confidence that the Service will successfully
address its refuge O&M backlog. He
said the Service will speak to this issue in its response to the states' joint
letter.
Marvin
Hubbell noted that the Service's January letter requested $300,000 and said he
assumed that the actual amount to be transferred will depend upon the costs of
the specific products that are identified in the scopes. Hubbell also noted that the Service's work
may reduce the Corps' own staff costs in some instances, meaning that the net
cost to the program may be somewhat lower than the actual amount transferred to
the Service. In response to a question
from Hubbell, Rhodes said the Corps will buy Service products as needed for
both refuge and non-refuge products.
Rhodes said Leo Foley, as EMP project manager, will be responsible for
ensuring that the Corps focuses on viable projects and does not buy products
for HREPs that will not be built.
While
the Corps is inclined to buy products from the Service for specific HREPs,
Rhodes emphasized that General Anderson has not yet made a final decision on
the Service's request. Moe expressed
Wisconsin's strong opposition to the Corps' proposed approach. He cautioned that expenses unrelated to
projects increasingly encumber the EMP.
Moe asked the other state EMP-CC members for their positions. Szcodronski noted that it is common practice
for federal agencies to transfer money to one another as needed for work on
specific projects and programs. As
such, he said Iowa supports the Corps' proposed response, subject to the
development of appropriate SOWs.
Farabee said Missouri will likely support the approach, citing the
accountability provided by the SOWs and the anticipated efficiency gains for
the program. However, Farabee said
Missouri will withhold its final judgment until the scopes are available for
review. Hubbell said Illinois is
prepared to support the proposed approach based on the preceding
discussion. He cited well-written, product-oriented
scopes and anticipated efficiency as key to Illinois' support. Hubbell also stated his assumption that the
costs for these Service-provided products will come entirely from the HREP side
of the program. Steve Johnson said
Minnesota opposes the transfer of planning or O&M funds to the Service, but has no objection to transferring money
for CARs and other specific products, assuming there are SOWs that the states
can review. Johnson said he would like
to review the Corps’ proposed approach after a year, including data on the amount
of money transferred and the estimated savings due to reduced Corps
workload. Rhodes said the Corps can
definitely provide figures on the amount of money transferred and will do its
best to measure cost savings.
Foley
repeated Blankenship's earlier point, reminding people that the Corps will buy
a variety of work from the Service, not merely the preparation of CARs. In response to a question from Szcodronski,
Foley said project fact sheets may be one such product. John Barko suggested that the Service might
be paid to do project performance evaluations.
Foley said the scopes will be shared with the other program partners as
they become available. Moe asked
whether there are SOWs for other administrative-type costs. Foley said there are not scopes per se for baseline monitoring and biological
response studies, but said something similar is prepared. Moe expressed interest in seeing
documentation of the Corps' administrative costs for the EMP. Szcodronski said he is not interested in
reviewing this information. Rhodes said
Wisconsin can seek an audit if it wants.
Moe said he is not asking for an audit, but merely to have information
similar to that which will be available for the money transferred to the
Service. Rhodes said he has tasked Ruff
and Foley with identifying ways to reduce overhead costs and put more money on
the ground. He indicated that MVD will
respond quickly to the Service's January letter.
Habitat Needs Assessment
Mike
Thompson explained that the HNA Technical Report is the entire body of
information used to produce the Overview/Summary Report and the Query
Tool. He reported that, on April 12,
the existing and forecast future conditions sections of the Technical Report
were forwarded to the Technical Team for review. A Beta version of the Query Tool was also distributed for review
in April, and the series of meetings with resource managers regarding desired
future conditions was completed on May 16.
Thompson said the Technical Team will hold another meeting to discuss
the resource managers’ desired future conditions, support needed for the Public
Involvement Team's focus group meetings, and final review of the HNA.
Thompson
reported that the public involvement focus group meetings are scheduled for
June and July. The SOW for the meetings
was completed on May 17, and the Public Involvement Team will meet with the
contractor prior to the focus group meetings.
In
contrast to the approach originally envisioned, the qualitative desired future
conditions input from the focus groups will not be synthesized with the more
quantitative desired future information from the resource managers. Instead, the focus groups’ and resource
managers’ perspectives will be presented in a parallel fashion in the final
report. Bob Clevenstine said there will
be an effort to identify areas of convergence and divergence between the
resource managers and the public.
In
response to various questions, Clevenstine said the Public Involvement Team and
contractor will determine the composition and size of the focus groups. Based on the team's earlier input,
Clevenstine said the plan is to separate the focus groups by interest rather
than having more heterogeneous groups.
The results of the resource manager meetings will be available to focus
group participants. Clevenstine said
the focus groups will consider the following questions:
·
Does
the Technical Team's characterization of the resource make sense? Is it understandable and relevant?
·
Do
they understand the Technical Team's assessment of forecast conditions?
·
Do
they understand the Technical Team's assessment of desired conditions?
·
What
are alternative expectations for desired future conditions?
·
What
are options and alternatives for future public involvement opportunities in the
EMP/HNA process?
Thompson
outlined the following steps for reviewing and submitting the final HNA:
·
Technical
Team completes review of draft Technical Report by 6/00.
·
Draft
Overview/Summary Report (technical portions only — i.e., exclusive of executive
summary, public involvement section, and final recommendations) is distributed
for review by EMP-CC and others on 7/31/00.
·
Comments
on draft Overview/Summary Report (technical portions only) are due 8/18/00.
·
Complete
draft Overview/Summary Report is distributed for review on 8/31/00.
·
Comments
on complete draft Overview/Summary Report are due 9/14/00.
·
Final
HNA is submitted to MVD on 9/30/00 (duplication of report for distribution will
await MVD review).
James
Falvey questioned the value of holding the focus group meetings if the results
of these meetings will not be reflected in the final report. Clevenstine clarified that the anticipated
qualitative input from the focus groups will not be integrated with the more
quantitative measures of desired future conditions expressed by the resource
managers. However, he emphasized that
input from both the focus groups and the resource managers will be fully
reflected in the HNA report. Dan Wilcox
noted that the focus groups were never intended to yield a quantitative
expression of the public's desired future conditions. He expressed optimism that it will be possible to identify areas
of convergence and divergence between the resource managers and the public.
In
response to a question from Gordon Farabee, Clevenstine indicated that the
information comprising the complete Technical Report will be available via the
internet and on CD. The relatively
brief, less technical Overview/Summary Report will be the primary vehicle for
broad distribution of the HNA. Wilcox
noted that the Beta version of the Query Tool is already proving to be a useful
river management tool. In response to a
question from Marvin Hubbell, Thompson indicated that the Overview/Summary
Report will include an assessment of the HNA's current applications and future
information needs.
Terry
Moe noted that the HNA uses information from the navigation study to forecast
future conditions. He expressed concern
that these navigation study data are incompatible with other data being used in
the HNA. Clevenstine replied that the
Technical Team agreed early in the process to use 18 habitat classes. He expressed confidence that the navigation
study data have been successfully translated into these 18 classes for use in
the HNA. He also noted that the
forecast future is essentially a visioning tool, explaining that the existing
and desired future conditions are the driving factors in determining habitat
needs.
Dusty
Rhodes expressed appreciation for Thompson and Clevenstine's interagency
teamwork in leading the HNA.
HREP Prioritization Process
Leo
Foley reported that the ad-hoc interagency group working to scope a new HREP
prioritization process revised its February 8 draft framework. These revisions were based on discussion at
the February EMP-CC meeting and written comments submitted subsequent to that
meeting. Foley reviewed the revised
framework, dated May 1, and offered his perspectives on the major comments
received:
·
Comment: There are too many new
teams. Response: The draft framework establishes only one new
team, making use of existing groups in all other instances.
·
Comment: Commenters offered various
perspectives on the composition of the teams, with some calling for outside
scientists on the System Ecological Team and others opposing such an approach. Response: Composition of teams remains to be determined.
·
Comment: Who determines the evaluation
criteria? Response: The teams will take the lead in developing
their own evaluation criteria.
·
Comment: Must be reasonable
consistency among fact sheets for system-level teams to do their work. Response: Don Powell will draft a fact sheet template for review and
consideration.
·
Comment: When will the new
prioritization process begin to influence funding decisions? Response: The process will likely be applied to new project planning starts
in FY 01. Projects already in planning
or construction will not be affected.
·
Comment: What about projects that have
previously been identified but for which planning has not been initiated? Response: Assume these projects will be considered under the new prioritization
process along with new project proposals.
Gordon
Farabee noted that people in the St. Paul and Rock Island Districts are
starting to develop pool plans.
According to Farabee, the to-be-formed St. Louis team will likely also
consider this approach. He urged that
the plans be sufficiently standardized to permit comparisons across
districts. Foley concurred, stressing
that the three districts should take compatible, though not necessarily
identical, approaches. He noted that
the Rock Island team envisions that its pool plans will identify work that can
be done under a range of programs, not merely the EMP. Dusty Rhodes said he shares Farabee's
concern regarding consistency, noting that one of MVD's challenges is to
balance efficiency and innovation.
Foley
said the Rock Island District is prepared to submit the prioritization
framework to MVD if the EMP-CC members are comfortable with the May 1
draft. Additional next steps include
selection of the System Ecological Team members and a request for the various
teams begin to develop their evaluation criteria. Jeff Stein asked whether there had been any consideration of
using the new process to review projects already in the pipeline. Foley said a wholesale review of current
projects would be inefficient and would threaten program execution. However, he said individual projects with
identified problems could be reviewed under the new process.
Kevin
Szcodronski said he believes the proposed process could work well. He suggested that the UMRCC Executive Board
members might serve as the core of the System Ecological Team, along with
representatives of the Corps and the Fish and Wildlife Service. Hubbell and Moe recommended that the Rock
Island District forward the draft framework to MVD. Moe said the System Ecological Team should include
representatives from each District Ecological Team, each state, the Fish and
Wildlife Service, and the LTRMP. Foley
suggested a conference call to discuss the composition of the System Ecological
Team. Dan Wilcox said the System
Ecological Team should work with the district teams in developing pool and
river reach plans to ensure that these plans add up to a system plan.
LTRMP Plans and Analyses for
Program Future
Leslie
Holland-Bartels distributed a revised version of the out-year plan developed at
the request of the A-Team and EMP-CC.
She stressed that data analyses should drive the out-year plan, but
acknowledged that there is something of a "chicken and egg" problem. Resources for such analyses are quite limited
under current funding levels. In
essence, the partnership needs the ramped up program to do the best job
possible designing the ramped up program.
As a result, Holland-Bartels recommended an iterative, "status and
analysis" approach, first designing a general plan for the future that can
be used as a basis for seeking increased funding and then refining that plan as
the increased funding permits more thorough analysis. She distributed a handout with a series of questions related to
spatial issues, efficiency of core programs, potential modifications to
monitoring, and other issues. For each
of the specific questions, the handout identifies the individual LTRMP work
items that are relevant to answering that question. Holland-Bartels explained that this approach allows people to
understand how various aspects of the LTRMP relate to answering the questions
in which they are most interested. In
response to a question from Dusty Rhodes, Holland-Bartels indicated that there
is a good partnership process in place for prioritizing information needs.
Holland-Bartels
gave several examples of how analyzing information needs can enhance program
focus and efficiency:
·
Systemic
models can provide information about areas not subject to direct
monitoring.
·
By
focusing on end users' information needs and reducing the number of land
cover/land use (LC/LU) categories, UMESC has been able to substantially reduce
the time and funding required to create systemic LC/LU coverages.
·
Using
the ArcView Model Builder application with the Query Tool permits more
sophisticated habitat prediction models that draw on more data and are less
likely to over-predict habitat suitability than the original Query Tool. This will be a powerful tool for use in the
HNA, HREP planning, and project monitoring.
She
noted that resource constraints will force the program partners to prioritize
among these opportunities. For example,
if people are anxious to take advantage of the refined Query Tool, then they
might emphasize obtaining additional data, such as bathymetry, and other things
needed to build that platform. In
response to a question from Rhodes, John Blankenship indicated that the refined
Query Tool could be quite useful in Endangered Species Act work, assuming that
the necessary data are available.
Holland-Bartels
explained that the technical staff's input regarding program priorities is
reflected in the draft out-year plan she distributed. She solicited the EMP-CC members' perspectives regarding
priorities and the format of the draft plan.
She also advised rounding‑off the current draft’s cost estimates
to eliminate their artificial precision.
Leo Foley expressed concern that people might equate the USGS and Corps
logos on the cover of the document with a commitment to fund the program at the
proposed levels. Holland-Bartels agreed
that it is important for the plan to reflect various uncertainties. Terry Moe praised the draft out-year plan
and Holland-Bartels' handout showing how specific tasks relate to answering
various key questions. He concurred
that the plan does not reflect a commitment to fund the LTRMP at specific
levels, describing it instead as a document designed to justify increased
funding. In response to questions from
Moe, Holland-Bartels and Jerry Skalak said the estimates for bathymetric and
elevation data are estimates and clarified that both LTRMP and non-LTRMP
funding sources will be considered for this work.
Holly
Stoerker said Holland-Bartels' handout is quite helpful in linking discrete
LTRMP tasks with the big picture decision process. She encouraged Holland-Bartels to incorporate this information
into the draft plan. Holland-Bartels
clarified that the handout currently reflects only her thinking and welcomed
input on how it might be incorporated into the draft plan.
Jim
Harrison asked how the sediment work being done under the LTRMP relates to the
sediment monitoring that may be authorized as part of Representative Kind's
Upper Mississippi River Basin Conservation Act (H.R. 4013). Holland-Bartels said she did not develop the
monitoring framework outlined in H.R. 4013, but indicated that she has talked
with the bill's proponents about the importance of coordinating with other
work, including the LTRMP's sediment monitoring and modeling.
Marvin
Hubbell complimented Holland-Bartels on her efforts to address future program
planning and on her overall management of the LTRMP.
Other Business
Holly Stoerker announced that future EMP-CC meetings
will be held on August 10 in the Quad Cities, November 16 in St. Louis, and
March 1 in the Twin Cities.
Dusty
Rhodes invited agenda item requests for the next meeting. Jim Harrison observed that there is no
EMP-CC meeting scheduled between the close of the HNA comment period and
submission of the final HNA to MVD. Rhodes
acknowledged this, noting that the Corps is statutorily required to complete
the assessment by September 30. Rhodes
expressed hope that the partners will not have extensive problems or comments,
given how involved they have been in developing the HNA. He said the August agenda will include time
to discuss the draft report.
Terry
Moe asked that the August agenda include a discussion of the System Ecological
Team proposed in the draft HREP prioritization framework. Kevin Szcodronski suggested that the August
agenda also include time to discuss the draft SOWs for the Service’s HREP
planning tasks.
With
no further business, the meeting adjourned at 11:51 a.m.
EMP-CC Attendance List
May 18, 2000
|
Dusty
Rhodes |
U.S.
Army Corps of Engineers, MVD |
|
John
Blankenship |
U.S.
Fish and Wildlife Service, Region 3 |
|
Leslie
Holland-Bartels |
U.S.
Geological Survey, UMESC |
|
Marvin
Hubbell |
Illinois
Department of Natural Resources |
|
Kevin
Szcodronski |
Iowa
Department of Natural Resources |
|
Steve
Johnson |
Minnesota
Department of Natural Resources |
|
Gordon
Farabee |
Missouri
Department of Conservation |
|
Terry
Moe |
Wisconsin
Department of Natural Resources |
|
Greg
Ruff |
U.S.
Army Corps of Engineers, MVD |
|
Tom
Pullen |
U.S.
Army Corps of Engineers, MVD |
|
Gary
Loss |
U.S.
Army Corps of Engineers, MVR |
|
Leo
Foley |
U.S.
Army Corps of Engineers, MVR |
|
Ken
Barr |
U.S.
Army Corps of Engineers, MVR |
|
Jerry
Skalak |
U.S.
Army Corps of Engineers, MVR |
|
Don
Powell |
U.S.
Army Corps of Engineers, MVP |
|
Dan
Wilcox |
U.S.
Army Corps of Engineers, MVP |
|
Deb
Foley |
U.S.
Army Corps of Engineers, MVS |
|
Mike
Thompson |
U.S.
Army Corps of Engineers, MVS |
|
John
Barko |
U.S.
Army Corps of Engineers, WES |
|
Bob
Clevenstine |
U.S.
Fish and Wildlife Service, Rock Island |
|
Jon
Duyvejonck |
U.S.
Fish and Wildlife Service, RIFO |
|
Tom
Boland |
Iowa
Department of Natural Resources |
|
Ken
Brummett |
Missouri
Department of Conservation |
|
John
Wetzel |
Wisconsin
Department of Natural Resources |
|
Dave
Beck |
Natural
Resources Conservation Service, Iowa |
|
Jim
Harrison |
Minnesota-Wisconsin
Boundary Area Commission |
|
Keith
Uhlig |
Minnesota-Wisconsin
Boundary Area Commission |
|
Jeff
Stein |
American
Rivers |
|
James
Falvey |
Mississippi
River Basin Alliance |
|
Dan
McGuiness |
National
Audubon Society |
|
Tom
Edwards |
River
Rescue |
|
Holly
Stoerker |
Upper
Mississippi River Basin Association |
|
Barb
Naramore |
Upper
Mississippi River Basin Association |