DRAFT
Minutes of the
Environmental Management Program
Coordinating Committee
February 21, 2008
Quarterly Meeting
Terry Smith of the U.S. Army
Corps of Engineers called the meeting to order at 8:10 a.m. on February 21,
2008. Other EMP-CC representatives
present were Don Hultman (USFWS), Linda Leake (USGS), Rick Mollahan
(IL DNR), Martin Konrad (IA DNR), Walt Popp (MN DNR), Janet Sternburg (MO DOC),
Gretchen Benjamin (WI DNR), and Al Fenedick (USEPA). Smith expressed Charles Barton’s regrets for
not being available to chair the meeting.
Minutes from the November 15, 2007 Meeting
Martin Konrad moved and
Gretchen Benjamin seconded a motion to approve the draft minutes of the November
15, 2007 EMP-CC meeting as written. The
motion carried unanimously.
Program Management
FY 08 Work Plan Overview
Marv Hubbell reported that,
with a $16.851 million appropriation, the FY 08 EMP funding distribution
includes the following:
·
LTRMP — $5.134
million
·
MVP — $3.365
million
·
MVR — $4.487
million
·
MVS — $3.365
million
·
Regional
management — $500,000
Hubbell further explained
that with the significant FY 08 funding constraints, each district will have
a choice as to whether to support continuation of the FY 07 LTRMP/HREP
integration effort this fiscal year. He
distributed the EMP spreadsheets for the first quarter of FY 08.
Hubbell also explained that
committee report language from Congressional appropriators bars the initiation
of new HREPs in FY 08, restricting funds to “ongoing design and construction
projects.” Under the Administration’s
interpretation of this language, the definition of “ongoing design” includes
those projects for which there was an expenditure of funds prior to FY 08 for
the development of a DPR. “Ongoing
construction” includes those projects for which there was a completed DPR and
an expenditure of funds prior to FY 08 for project engineering, design, or
construction. Hubbell said this allows
for the completion of DPRs already in development, the award of contract
options or task orders on existing contracts, and the award of additional
construction contracts that would support continued implementation of a DPR.
President’s FY 09 Request
Hubbell reported that the
President’s FY 09 budget request includes $20.0 million for the EMP. He also explained that, if Congress were to
extend its restrictive language on new starts to FY 09, this would have
significant adverse effects on the HREP program, with MVS experiencing the greatest
difficulty. Assuming no such
restrictions in FY 09, and appropriation at the President’s requested $20.0
million level, the FY 09 program would include planning or design on 16
projects, construction on 7 projects, and the collection of related data. If the restrictive language were extended,
Hubbell said construction would only be possible on 3 of those 7 projects.
Hubbell distributed one-page
summaries for each state, highlighting the EMP’s accomplishments. He asked EMP-CC members to review the
summaries and apprise him of any errors.
Gretchen Benjamin noted that the summary sheets reflect lower figures
for expenditures and acres benefited than have been previously reported. Hubbell said he didn’t think there have been
any substantial corrections to the expenditure numbers, but explained that some
previous overestimates on acres benefited have been corrected. He added that the methodology used to
calculate acres benefited has not been rigorously consistent over the EMP’s
history and across districts.
EMP Management
Hubbell observed that
authorization of NESP, and Congressional restrictions on how EMP funds are
spent in FY 08, raise obvious questions about future management of the
EMP. Hubbell said MVD’s clear guidance
is to plan for the EMP as a fully functioning program going forward. The districts are not assuming that the FY 08
restrictions will necessarily be extended beyond this year. So, for example, MVR will be working this
year to ready the
Public Involvement
Hubbell reported that the
Corps has entered into a new agreement with the
Hubbell said the itinerary
for the display has not been established, but encouraged partners to contact
Justine Barati with their recommendations.
Gretchen Benjamin said she would like to see the display in
Don Hultman reported that
groups working through the National Refuge Friends will be visiting
Habitat Rehabilitation and Enhancement
Projects
FY 08 Work Plan
Don Powell reported that MVP
will devote approximately 75 percent of its FY 08 allocation to
construction. Planning efforts will
continue on Capoli Slough and Harpers Slough, but have been deferred on three
other projects that the district had previously intended to initiate. Design efforts will focus on the Finger/Clear
Lake HREP and Pool 8 Islands Phase III Stage 3.
With more funding, Powell said Pool 8 Phase III Stage 3 could be ready
to advertise this year. MVP’s FY 08
construction efforts will focus on Pool 8 Islands Phase III Stages 2A and
2B. Stage 2A is nearing completion. There is a $1.9 million option available on
Stage 2B this year. The district’s
channel maintenance program is paying to transport some of the dredged material
needed for Pool 8 from a nearby disposal site.
Powell said MVP will try to extend the award date of remaining Stage 2B
options into next year.
Janet Sternburg asked whether
the Corps goes back to address performance issues or negative effects when they
are noted in project evaluation reports (PERs).
Powell said the Corps can and has done this, citing the Finger/Clear
Lake HREP as an example. He explained
that the original
In response to questions from
Sternburg, Markert explained that delays in the Ted Shanks project are due to
funding constraints, not the restrictive committee report language. The Ted Shanks project was far enough along
in planning so as to qualify as an “ongoing design” effort. With the funding-related delays, Markert now
estimates that the DPR for Ted Shanks should be completed in FY 10. He also noted that steel and rock costs have
increased significantly, raising costs on projects that require large
quantities of these materials.
Hubbell reported that
HREP Bioresponse Monitoring Report
Hubbell reported that, in
response to EMP-CC members’ requests, Charlene Carmack had worked with other
Corps staff to develop an overview of HREP bioresponse monitoring to-date. Hubbell observed that the three districts’
approaches have varied substantially in terms of the number of projects
monitored and the intensity of that monitoring.
Explaining that Carmack looked only at direct monitoring of organisms
and mostly at work done or funded by the Corps, Hubbell summarized the
districts’ efforts as follows:
·
8 of 23 HREPs in
MVR have had some bioresponse monitoring, with fisheries surveys on 6 of those
projects, vegetation surveys on 5, and wildlife surveys on 3;
·
2 of 23 HREPs in
MVS have had some bioresponse monitoring, with vegetation surveys on both
projects and fisheries and wildlife surveys on one of the projects; and
·
7 of 31 HREPs in
MVP have had some bioresponse monitoring, with fisheries surveys on all 7
projects and vegetation surveys on 6 of the 7 projects.
Hubbell summarized some of
the insights gained, including findings regarding the relative success of
various approaches to revegetation; overall fisheries, vegetation, and wildlife
response; and post-project changes in human use patterns. He noted that MVS has done bioresponse
monitoring on fewer projects, but that its monitoring was relatively
intensive. Markert clarified that MVS
did both fisheries and waterfowl monitoring on
Hubbell asked whether this report
on past bioresponse monitoring was responsive to the EMP-CC members’ request. Sternburg expressed her appreciation for
Carmack’s efforts and asked how partners can access the bioresponse data and
reports. Hubbell said the Corps would
work to ensure that bioresponse, as well as chemical and physical, monitoring
results are available to EMP partners.
Barb Naramore suggested that making project monitoring reports available
as part of the HREP database would be quite helpful. Hubbell explained that some of the results
are developed into formal reports, while others are captured more informally in
things like site visit reports.
Depending on how the information is captured, it may reside in different
places. Gretchen Benjamin emphasized the
need to ensure long-term data accessibility.
In answer to a question from Walt Popp, Powell said physical and
chemical response data may be available prior to release of the evaluation report. Powell suggested that Popp contact Dan Wilcox
for such advance access to monitoring data on MVP projects.
Hubbell strongly encouraged
the states and Fish and Wildlife Service to provide the appropriate district
HREP coordinator with the results of any project monitoring that they
conduct. He observed that non-Corps
staff do a fair amount of such monitoring outside of the formal post-project
evaluation plan, but that the results are often not incorporated into project
evaluations.
In response to a question
from Sternburg, Hubbell said specific projects have been selected for
bioresponse monitoring for a variety of reasons in the past. For example, he said the Pool 11 Islands HREP
was selected because its design lent itself to exploring the optimal spacing
between patches of overwintering habitat for fish. With
Barry Johnson asked whether
the EMP has ever developed a project with the intent of answering a specific
question. Hubbell said that, by and
large, the EMP has not used this approach.
However, he noted that the Pool 12 project is designed to answer
questions about the physical relationship of features and their outcomes. Hubbell said this is the first time an HREP
has been designed to test a hypothesis.
HREP Showcase
Markert presented an HREP
showcase highlighting the
Overall, Markert described
the project as a success. Among the
significant indicators of success, water quality has improved; wind fetch, wave
formation, and turbidity have been reduced; aquatic plant growth has increased;
and waterfowl response has been strong.
However, operationally, the function of the pump on the lower management
unit has presented some challenges.
Specifically, managers can’t de-water the unit sufficiently to
effectively consolidate sediments.
Efforts are underway to address this problem. In addition, since construction,
According to Markert, next
steps with the
Long Term Resource Monitoring Program
Key Findings/Products
Linda Leake reported that FY
08 first quarter highlights for the LTRMP include three project completion
reports and one manuscript, addressing the following topics:
1.
Importance of the
UMR forest corridor to neotropical migrants (completion report)
2.
Development of a
demonstration floodplain forest restoration database for the UMRS (completion
report)
3.
Evaluation of Hydrolab
self-cleaning turbidity sensor (completion report)
4.
Reduced condition
factor of two native fish species coincident with the invasion of Asian carp in
the
FY 08 Proposed Scope of Work
Leake said the minimum
sustainable program (MSP) scope for FY 08 has been developed. It includes monitoring the three core
components (i.e., fish, water quality, and aquatic vegetation), analysis and
reporting, statistical evaluation, data management, GIS support, and bathymetry
support. The milestone spreadsheet
contained in the meeting packet includes anticipated product delivery dates for
the MSP work.
Leake reported that, of the 15
technical Additional Program Element (APE) proposals for FY 08, six have been
selected for funding. According to
Leake, the selected projects all address one of the five focal questions and
were ranked high or medium-high by USACE, USGS, and the A-Team. The funded APEs include:
1.
developing an
empirical framework for reconstructing and modeling UMRS floodplain disturbance
histories;
2.
setting
quantitative fish management targets for LTRMP monitoring;
3.
developing survey
methods to map mussel assemblages in the UMRS;
4.
analysis of
aquatic vegetation sampling data in Pools 6, 9, 18, and 19;
5.
experimental and
comparative approaches to determine factors supporting or limiting submersed
aquatic vegetation in the
6.
hydrologic
connectivity between off channel areas and the main channel.
Leake
observed that the later in the fiscal year APE funds are awarded, the harder it
is for investigators to complete their work in the same fiscal year. She said the flexibility to carry funding
forward into FY 09 for completion will help ensure that the investigators
have sufficient time, given the late decisions on the FY 08 APE projects. Leake also emphasized the importance of the
investigators meeting the schedules to which they agree. Noting that product delays are problematic
for the entire LTRMP, Leake said UMESC is prepared to assist investigators
where possible in meeting their deadlines.
Leake reported that the Corps
and USGS are recommending funding for the following administrative APEs in FY
08:
·
basic field
station equipment refreshment ($60,000 out of $130,000 in identified needs),
·
completing the
LTRMP Strategic Planning effort,
·
support for data
visualization tools,
·
an annual meeting
for field station personnel (planned for June in
·
publications, and
·
continuing the
LTRMP/HREP integration effort.
Marv Hubbell noted that, when
the distinction was made last year between technical and administrative APEs,
it was agreed that the Corps and USGS would coordinate directly with the EMP-CC
regarding administrative APEs, rather than through the A-Team. He then went on to explain that the Corps and
USGS have not included the restored monitoring project as part of their
recommended package of administrative APEs for FY 08, electing instead to
present three possible options for the EMP-CC partners’ consideration. Those options are as follows:
1.
one or more
medium-ranked technical APEs,
2.
additional field
station equipment refreshment, or
3.
restored water
quality and fisheries monitoring.
According to Hubbell, the
restored monitoring would require approximately $74,000, and that is roughly
how much is available after funding the recommended package of other administrative
APEs.
Barry Johnson explained that
the four medium-ranked APEs available for consideration would each individually
cost less than $74,000. He briefly
summarized each of those project proposals:
1.
continued
evaluation of emergent vegetation response to water level management on Pools 5
and 8 through the collection and interpretation of aerial photos ($40.9k)
2.
matching
indicators to management objectives using statistical criteria ($37.5k)
3.
conceptual
modeling of river ecosystem structures, functions, and services influenced by
floodplain connectivity ($49.5k)
4.
statistical and
geospatial analyses of mussel communities on the UMR ($57.7k)
With regard to the equipment
refreshment option, Leake explained that $60,000 in mission-critical items
would be funded under the administrative APE package being recommended by the
Corps and USGS. The remaining $70,000
presented as an alternative to the restored monitoring or the technical APEs
consists of additional needs identified by the field stations, but not characterized
as critical. Leake also explained that
USGS did not make any effort to review or equalize the equipment needs
identified by the field stations.
Martin Konrad asked for
clarification regarding the option to add one or more medium-ranked technical
APEs, noting that any two of them would exceed the $74,000 said to be
available. Hubbell said a decision to
fund two additional projects would mean some offsets would have to be
identified elsewhere in the LTRMP budget, such as the meeting for field station
personnel. Leake suggested another
option would be to prioritize a first and second choice among the medium-ranked
APEs, deferring final approval on the second project until the LTRMP’s overall
funding picture firms up. If sufficient
funds are not available to support the second project, than whatever funds are
available could be put toward additional items on the equipment refreshment
list.
Responding to the options
presented by the Corps and USGS, the other EMP-CC members expressed the following
priorities and perspectives:
·
Wisconsin — top
priority is restored monitoring; 2nd choice is the water level
management and indicators APEs
·
·
Iowa — top
priority is restored monitoring; 2nd choice is the water level
management and indicators APEs; understands that March 31 is now the deadline
for the pending FY 07 restored monitoring report and believes this same
timeline should be used in FY 08
·
·
·
USFWS — top
priority is the mussel communities APE and additional equipment refreshment;
Service has been seeking additional mussel information for some time; this is
particularly critical now that drawdowns are becoming almost routine; concerned
with the precedent of funding an ongoing project when products are not being
delivered
·
USEPA — defers to
states and USFWS, but thinks equipment refreshment is important to the LTRMP’s
viability and that the restored monitoring project has merit
Leake said all investigators
have been cautioned that late products will affect their eligibility for new
work. She stressed the need for all
project proposals to include realistic timelines. Walt Popp said the states were remiss in
agreeing to a December 31 deadline for the restored monitoring report, observing
that the fisheries data QA/QC is not even completed until December or
January. Gretchen Benjamin asked about
the possibility of an interim progress report.
Leake said this was explored, but the investigators concluded there was
not sufficient information available to do anything meaningful. She emphasized that, when unforeseen
circumstances force the delay of a product, the investigator needs to work with
UMESC managers and the Corps to agree upon a revised schedule.
Hubbell said he found the
preceding discussion to be very helpful and healthy. Benjamin expressed appreciation for the
advance materials, saying they provided her with the information she needed to
make the decision being asked of her.
Hubbell said he understood the perspectives offered by the states and
Service, not just concerning relative priorities but also regarding the issue
of product delays and the importance of timely information.
LiDAR and Bathymetry
Hubbell announced that Hank
DeHaan has received a promotion and will now be serving as MVR’s program
manager for the Illinois River Section 519 program, as well as the
environmental continuing authorities programs in the district. Hubbell said MVR will name a temporary LTRMP
manager, and then fill the position permanently in a few months.
DeHaan reported that no new
LiDAR or bathymetry data collection is being initiated under EMP in FY 08,
due to fiscal constraints. However, the
cooperative effort between the Corps and
DeHaan further explained that
the ongoing cooperative effort between the Corps and
Status and Trends Report
Johnson reported that he is
in the process of addressing comments from the USGS editorial staff on the
Status and Trends Report. He estimated
that this process should be completed within the next couple of weeks, after
which the report will go to the publisher.
The final Status and Trends Report should be available in April or May. Johnson also distributed copies of the draft
report, explaining that this version reflects responses to stakeholder
comments, but not to the editors’ comments.
He also said a document describing how USGS responded to all of the
stakeholder comment is available upon request.
Information Access
Leake recalled that, at its
November 2007 meeting, the EMP-CC had a fairly extensive discussion concerning
the need to balance timely information access with publication in peer-reviewed
journals. She noted that journal
publication is by far the lengthiest process.
USGS’s own internal review process for its publications is much shorter,
but still requires several weeks, under the best of circumstances. She described USGS’s internal process, which
applies to all documents circulated to the public, as follows:
·
Author submission
·
Supervisor
approval (1-2 weeks)
·
Peer review (3
weeks)
·
Back to author
(1-2 weeks)
·
Supervisor
ensures comments were addressed (1-2 weeks)
·
Editorial review
(1-2 weeks) (not required for some publications, such as completion reports)
·
·
Bureau approval
(1-2 weeks)
·
USGS publishing
network
Leake said USGS managers are
well-aware of the need to ensure timely access to information while preserving
their staff’s ability to publish in journals, an essential part of their
professional advancement. She identified
the following three options for accelerating access to LTRMP findings:
1.
Increased use of
presentations, such as the A-Team has been requesting at its meetings of late
2.
Expanded
distribution of project completion reports — in order to do this, the released
report would be a one page summary, similar to an expanded abstract; no
manuscript would be attached; USGS would submit these reports to USACE, which
would then be responsible for forwarding them to the program partnership; more
internal review steps would be required if USGS were to distribute the
completion reports directly to the full partnership
3.
More use of
open-file reports prior to manuscript publication — these are citable,
published reports; they would be shorter than the manuscript and would need to
have a different title, but might be a good option when the completion report’s
expanded abstract approach does not provide sufficient detail
Leake said USGS will survey
program partners regarding their preferences for receiving information and get
back to the EMP-CC with its findings and recommendations.
Leake recalled that, at the
November EMP-CC meeting, Gretchen Benjamin had suggested creating some kind of
centralized documentation of the questions that have been asked under the LTRMP
and the resulting answers. As a first
step in exploring this possibility, Leake said she would like to make certain
that people understand how they can currently access existing LTRMP
products. She provided the following
summary:
·
LTRMP Reports
(includes program, reprint, special, & technical reports)—these number 300
and are all available in the UMESC library; all are also listed online, with
reports from 2000 forward available online as PDFs
·
Project Status
Reports — these number 50 and are all available online
·
USGS Fact
Sheets/Open-File Reports — these number 4 and are all available online
·
Web Annual
Component Updates/Reports — these number 16 and are all available online
·
Manuscripts — these
number 80 and are all listed online; reprints should be requested of the author
Documents on UMESC’s web site
are searchable.
Leake said it would be
possible to tease out questions and answers from the LTRMP’s more than 400
publications, in the form of a bibliography or software application. But she cautioned that this would be a
considerable undertaking and said USGS needs more specificity regarding what
people want before it could develop a meaningful scope and cost estimate. Benjamin said the impetus for her suggestion
in November was concern that we capture what we’ve learned more effectively
before institutional memory erodes through retirements. Without such a centralized system, Benjamin
said she is concerned that LTRMP will expend resources unnecessarily re-asking
questions.
Leake observed that it could
be quite costly to go back in time to create such an inventory. Documenting questions asked and insights
gained moving forward would be a simpler task, according to Leake. Benjamin acknowledged this and suggested that
the first step might be to create a system for ongoing and future work,
deferring a decision about whether to go back in time. Barb Naramore said one significant challenge
would be to ensure sufficient consistency among the database’s entries that they
can be searched effectively on something other than very broad terms. This would be particularly challenging over
time and across multiple investigators, she observed. DeHaan noted that NESP’s decision support
system includes a knowledge component, using a keyword approach. He encouraged partners to keep the EMP and
NESP efforts aligned in this area.
Johnson cautioned that such a
database would not give users a systemic perspective on the questions asked and
insights gained. That perspective, he
explained, requires someone to synthesize the information. Leake reported that UMESC has a new librarian
on staff who is very conversant with information access issues and available
software tools. Leake said this person
could explore options for developing a searchable database of LTRMP research
questions and findings.
A-Team Report
Sternberg distributed a
written A-Team report, summarizing the Team’s January conference call. She expressed the A-Team’s appreciation to
USGS and USACE for their efforts to improve timely access to LTRMP
information. She said the A-Team is also
pleased with the renewed emphasis on timely product completion.
Strategic Planning Update
Hubbell reported that the
LTRMP Strategic Planning Team held its fourth meeting on December 17-19. At this meeting, the team worked further on
the draft outcomes (i.e., goals) and outputs (i.e., specific products that
support the goals), focusing primarily on refining their scope and articulating
their interrelationships. Hubbell said
the December meeting also included considerable discussion of how these
outcomes and outputs will further LTRMP’s ultimate mission of informing
decision makers and river managers.
Questions of relative priority among the outcomes and outputs, and how
that relates to the allocation of inputs (i.e., resources needed to support the
desired outcomes and outputs), remain to be addressed.
Hubbell encouraged program
partners and stakeholders to convey any comments or concerns to their point of
contact on the Planning Team. He said
the team has worked hard to maintain an open process and is genuinely
interested in receiving input at any time.
The Planning Team is scheduled to meet again in March, after which it
will issue a review draft of the plan for stakeholder comment. The team will reflect on those comments at
its July meeting, with the intent of providing a revised plan for the EMP-CC’s
consideration at its August meeting.
EMP/NESP Integration Issues
Chuck Spitzack emphasized the
need to implement NESP and EMP as separate programs, but in a coordinated
fashion, unless and until the Corps is directed to do otherwise. He described the Corps’ approach to
developing the required NESP implementation reports to Congress, the first of
which is due in June 2009. Spitzack said
the NESP leadership team will be creating a statement of work on how to develop
the report. Various implementation teams,
such as the four reach planning teams, system planning team, and Science Panel,
will then have responsibility for developing different parts of the report. The June 2009 report will address baselines,
milestones, goals, and priorities for the NESP ecosystem restoration projects.
Regarding institutional
arrangements (IA), Spitzack characterized the 2005 partner workshops as having
been extremely productive. He said the
input from those workshops provides an important base upon which the Corps can
build as it renews its consideration of IA issues now that NESP has been authorized. Spitzack explained that Corps staff have been
reviewing the NESP authority’s Advisory Panel requirements as well as previous
IA proposals and comments on those ideas.
He said the Corps wants to avoid an IA structure that would be subject
to the Federal Advisory Committee Act (FACA), and observed that the UMRBA’s
proposal to add NGO representation to a combined EMP-CC and NECC would appear
to trigger FACA. Spitzack invited
further partner comment and suggestions.
Martin Konrad said the state
EMP-CC representatives, as well as the UMRBA members, are concerned that a
clear partnership consensus on future institutional arrangements has not
emerged, despite extensive discussions in the past. While stressing that it is not the states’
intent to leave anyone out, Konrad said the previous large group discussions
have simply been too wide-ranging and unfocused to be effective. As an alternative approach, Konrad said the
state EMP-CC members are proposing a more focused effort, under which a small
work group, selected to include a range of relevant perspectives, would be
charged with discussing IA needs and options.
That group would then report back with a package of recommendations for
the full partnership’s consideration in May.
Konrad said he hoped that Rebecca Soileau would be able to coordinate
and facilitate this small group.
Konrad identified the
following proposed membership for the small IA group:
·
Terry Smith (MVD)
·
Chuck Spitzack
(NESP Manager)
·
Ken Barr (NECC
Chair)
·
Marv Hubbell (EMP
Manager)
·
·
Linda Leake
(USGS, LTRMP)
·
Catherine
McCalvin (TNC)
·
Paul Rhode (WCI,
ECC)
·
Gretchen Benjamin
(EMP-CC, NECC, district groups)
·
Janet Sternberg
(EMP-CC, A-Team, NECC, district groups)
·
Barb Naramore
(UMRBA)
Gretchen Benjamin emphasized
that the proposed small group would simply be coming up with a working draft to
present to the broader partnership. She
said she views this as a way of getting this important IA discussion moving
again. Jon Duyvejonck expressed concern
that the work of the old IA project delivery team (PDT) would be set
aside. Konrad said that is not the
intent. Rather, the states believe that
the IA PDT is too large and its previous discussions too unfocused. Konrad expressed optimism that a smaller,
more nimble group could work through the current issues and come back to the full
partnership with a viable proposal.
Benjamin said the new IA group would certainly consider the IA PDT’s
previous work. But she also emphasized that
the larger group had not reached a consensus when its efforts were put on hold
back in 2005. Specifically, Benjamin
noted that there was a draft on which many parties, including the UMRBA,
commented extensively. To-date, the
Corps has not responded to those comments.
Soileau said she is
encouraged by the individuals apparently willing to work on the states’
proposed group. She acknowledged the
past challenges in working with a 40-person IA PDT. Soileau said she is currently working on some
products, including a cross-walk of the various IA proposals that have been put
forward, that would likely be quite helpful to the small group in its work.
In response to a question
from Konrad, those individuals suggested for the small group who were present
affirmed their willingness to serve on the group.
Benjamin moved and Fenedick
seconded a motion expressing the EMP-CC’s support for the approach outlined by
Konrad, with the goal of having the small group report back to the NECC/ECC,
EMP-CC, and UMRBA in May with its IA recommendations. The motion carried unanimously. The EMP-CC members asked Konrad to present
the proposal to the NECC tomorrow for that group’s consideration.
Other Business
Ken Barr recommended that the
EMP-CC and NECC consider meeting jointly on the afternoon of May 21, 2008.
Barb Naramore announced that
the upcoming quarterly meetings are schedule as follows:
·
May 2008 — Twin Cities
o
UMRBA — May 20
o
NECC/ECC — May 21
o
Joint NECC/ECC and EMP-CC — afternoon of May 21 (if needed)
o
EMP-CC — May 22
·
August 2008 —
o
UMRBA — August 5
o
EMP-CC — August 6
o
Joint EMP-CC and NECC/ECC — afternoon of August 6 (if needed)
o
NECC/ECC — August
7
·
November 2008 — Quad Cities
o
UMRBA — November
18
o
NECC/ECC —
November 19
o
Joint NECC/ECC and EMP-CC — afternoon of November 19 (if needed)
o
EMP-CC — November 20
With
no further business, the meeting adjourned at 12:25 p.m.
EMP-CC Attendance List
February 21, 2008
EMP-CC Members
|
Terry Smith |
|
|
Don Hultman |
|
|
Linda Leake |
|
|
Al Fenedick |
|
|
Rick Mollahan |
Illinois Department of
Natural Resources |
|
Martin Konrad |
Iowa Department of Natural
Resources |
|
Walt Popp |
Minnesota Department of
Natural Resources |
|
Janet Sternburg |
Missouri Department of
Conservation |
|
Gretchen Benjamin |
Wisconsin Department of
Natural Resources |
Others in Attendance
|
Don Powell |
|
|
Rebecca Soileau |
|
|
Jeff DeZellar |
|
|
Chuck Spitzack |
|