Minutes of
the
Environmental
Management Program
Coordinating
Committee
February 22, 2006
Quarterly Meeting
Renaissance Airport Hotel
Charles Barton of the U.S. Army
Corps of Engineers called the meeting to order at 11:30 a.m. on February
22, 2006. Other EMP-CC representatives
present were Charlie Wooley (USFWS), Mike Jawson (USGS), Rick Mollahan (IL
DNR), Martin Konrad (IA DNR),
Tim Schlagenhaft (MN DNR), Janet Sternburg (MO DOC), Gretchen Benjamin (WI DNR),
and Al Fenedick (USEPA). A complete
list of attendees follows these minutes.
Announcements
Charles Barton announced that Marvin Hubbell has been named as the Corps’ new EMP Program Manager. In addition, Martin Konrad and Mike Jawson are the new EMP-CC representatives for the Iowa Department of Natural Resources and the U.S. Geological Survey, respectively.
Minutes of the November 16, 2005 Meeting
Gretchen Benjamin noted that “bathymetry” was misspelled in one location on p. 5 of the draft minutes. Benjamin moved and Janet Sternburg seconded a motion to approve the draft minutes of the November 16, 2005 meeting, with the spelling correction identified by Benjamin. The motion carried unanimously.
Program Management
FY 06 Implementation Update
Through the first quarter of FY 06, obligations totaled $2.9 million and expenditures were $2.3 million. Hubbell characterized these as typical rates for this point in the fiscal year. He explained that both obligations and expenditures usually pick up in the second and third quarters, with the seasonal increase in HREP construction activity and transfers to USGS and the states for the LTRMP.
Hubbell reported that Corps staff briefed Assistant Secretary Woodley (ASA CW) regarding the 2004 Report to Congress on December 21, 2005. Secretary Woodley was enthused about the program, describing the EMP as a success story. The Secretary has forwarded the report to the Office of Management and Budget and the Congress.
Hubbell highlighted three major changes in the FY 06 energy and water appropriations bill that are affecting implementation of the EMP:
Due to the prohibition on
continuing contracts, the
Janet Sternburg expressed
concern with the prospect of reducing the LTRMP allocation to augment HREP
funding. She asked whether the estimated
unmet HREP needs represent current contractual commitments. Hubbell said the Pool 11 Island and Calhoun
Point contracts have been let.
Tim Schlagenhaft sought
clarification on the timing of decisions, noting that he would like an
opportunity to explore the implications with
1. The Corps has already decided not to obligate the $805,000 to the LTRMP.
2. In May, the Corps will know if the actual unmet need for the two Districts is greater or less than the $1.49 million estimate. At that point, the Corps will make further decisions based on this information. Corps staff will consult with program partners in making those decisions.
In response to a question from
In response to a question from Sternburg, Perk said indefinite delivery contracts may be one means by which the EMP can adapt to the new contracting environment. Hubbell said the Corps will confer with its partners as program staff make necessary adjustments and start to plan for FY 07.
District HREP Reports
Don Powell reported that the St.
Paul District can operate within its FY 06 allocation of $3.91 million. More than half of this amount is already
obligated, due largely to the
Brian Markert reported that
planning for Ted Shanks and
Acknowledgments
President’s FY 07 Budget Request
Hubbell also reported that Corps staff have used the HREP database to develop program fact sheets for each Congressional district. Once the format is approved, these fact sheets will be available to program partners and stakeholders.
Public Outreach
EMP 20th Anniversary
Holly Stoerker observed that the states and the UMRBA might be particularly well-positioned to execute certain aspects of a celebration plan that would not be as appropriate for the federal partners. This would include, perhaps, thanking members of Congress and the Administration for their support of the program. She also noted that the UMRBA is celebrating its 25th anniversary in 2006 and will be showcasing various activities at its quarterly meetings. The tentative plan is to focus the August meeting on the EMP. She said this might be a good opportunity to coordinate the EMP and UMRBA celebrations.
Benjamin stressed the importance of including a public focus in the overall celebration, rather than limiting it to program insiders and decision makers. Martin Konrad agreed, noting that NGOs and river cities are important players.
Hubbell asked for an indication
of who would be willing to serve on an anniversary planning committee. Representatives of the Corps, Service, USGS,
Public Involvement and Program Advocacy
Don Powell reported that the St.
Paul District issued a press release when it awarded the Pool Slough
contract. MVP also provided an EMP
display for a special multi-agency public outreach event in January at the Mall
of America in the Twin Cities. Powell
thanked Fish and Wildlife Service staff for providing informational signs for
display at HREP construction sites. He
noted that the Service also frequently develops more permanent informational
kiosks at completed projects.
Long Term Resource Monitoring Program
FY 06 Scope of Work
LTRMP Product Status Update
Jawson said USGS and the Corps have agreed that ensuring the quality and utility of the pending Status and Trends Report is more important than adhering to a strict deadline. Analysis, synthesis, and information dissemination will be key functions of the report. According to Jawson, the current schedule calls for a draft report to be available for A-Team and EMP-CC review on March 1, with comments due on April 1 and the draft to be submitted for editorial review on May 1. The remainder of the schedule through publication remains to be determined.
In response to a question from Chuck Theiling, Jawson confirmed that the completed Status and Trends Report will not be available during this summer’s 20th anniversary events. However, he went on to explain that key information, conclusions, and other highlights may be released prior to the full report’s publication. As an example of such a finding, Jawson said that, on some sections of the river, 70 percent of the fish biomass is comprised of exotic species.
MSP in FY 07
Currently, EMAP funding from U.S. EPA helps support some staff capacity that is also used to execute the MSP. The future for EMAP in FY 07 and beyond is uncertain. However, Jawson stressed that the LTRMP will continue to seek opportunities to collaborate with EMAP.
Each LTRMP partner agency has been asked to develop a five-year plan for equipment refreshment, with the plans covering FY 07 to 11. The annual refreshment target is one percent of MSP funding. Jawson explained that equipment refreshment in FY 06 exceeded this one percent figure because there were carryover funds available.
In May, the Corps will have a firm estimate of its unmet HREP needs, at which point it will be known whether any of the $805,000 in holdback funds will be made available to the LTRMP. However, Jawson explained that, by May, it will be too late in the fiscal year to use any additional funds to execute LTRMP projects. Instead, USGS is working with the states to develop a flexible list of equipment purchases that would enhance program performance in future years. Examples might include survival suits and total nitrogen and phosphorus analyzers. Jawson encouraged all partners to submit ideas for additional items.
FY 06 APE Update/FY 07 APE Process
Jawson reported that agency staff submitted more than 50 APE proposals for FY 06. Ultimately, 15 APE projects were selected for funding. Participants expressed two principal frustrations with the process for FY 06:
USGS is currently working with the Corps, A-Team, and field stations to identify themes for FY 07, with the goal of better targeting project proposals to priority information needs. According to Jawson, the timeline for FY 07 APE project development and selection includes the following:
Ken Lubinski observed that
delays in the appropriations process frequently mean the actual budget is not
known until well into the fiscal year.
This leaves less than 12 months to complete APE projects, potentially
undermining the projects, which would already be quite constrained even with a
full 12 months. Jawson acknowledged this
difficulty, along with the related constraint imposed by the requirement for
one-year products for all APEs. He said
this makes in-depth work difficult and urged partners to think creatively about
useful interim products that could build logically as part of a longer term
effort.
Martin Konrad observed that the MSP and APEs appear to compete for funding. He asked whether the partners were satisfied with the MSP. Hubbell acknowledged that there are different levels of satisfaction among the partnership. He explained that the MSP was devised to provide a level of stability for the monitoring effort over a period of five years. While many people would have preferred a larger MSP, it was set at the maximum possible size given assumptions about inflation — i.e., at the end of the five years, there will be no APE money.
Konrad said that $1 million seems high for APEs in FY 06 and asked whether more monitoring could be done. Hubbell said expanding monitoring is problematic because there is no guarantee that increased funding in one year will be sustained the following year. Jawson noted that the restructured program also reflects a fundamental philosophical position regarding the need for balance between data collection and evaluation. He said merely collecting more data without the capacity to analyze it is not productive. The APEs provide the opportunity for analysis and evaluation. Roger Perk concurred, recalling that the partner agencies made a conscious decision that the LTRMP needed to do analysis and research. Prior to the LTRMP restructuring and the introduction of the MSP and APEs, monitoring had squeezed research and analysis out of the program almost entirely.
A-Team Report
Regarding the earlier discussion about the MSP, Maher explained that none of the A-Team members are happy with the MSP from a biological perspective. The MSP under the restructured program reflects a budget-driven approach, rather than members’ judgment about what would be truly adequate. From a biological perspective, Maher said the A-Team views the FY 02 sampling program as having been adequate. According to Maher, the A-Team will devote a portion of its April meeting to developing a contingency sampling plan should additional monitoring money be available in FY 07. He acknowledged the difficulty of enhancing monitoring given budget uncertainties and the LTRMP’s other obligations.
Habitat Rehabilitation and Enhancement Projects
Hubbell explained that work on
the HREP database was delayed because a key staffer was diverted to hurricane
duty. That person has now returned and
is working to convert the HREP data from Access to a GIS environment. In response to a question from
Hubbell reported that the System Ecological Team’s (SET’s) evaluation and sequencing document was revised subsequent to the November 2005 EMP-CC meeting at which it was presented. Of note, the project scoring approach was eliminated in favor of a criteria checklist. Hubbell stressed that the Corps views the revised document as a working draft. The SET will test the current version this spring, using HREP proposals from all three districts. Hubbell said the evaluation and sequencing document will then be revised further as necessary based on that experience. Tim Schlagenhaft expressed confusion regarding the process and the relationship between the SET and the Science Panel. He noted that the Pool 5 planning team had not been informed of the shift to a checklist approach and thus has not adjusted its work accordingly. Hubbell acknowledged that all of the necessary communications have not yet taken placed. But he said the Corps will ensure that the district ecological teams and pool planning teams are kept in the loop as the SET refines its approach.
EMP/NESP Merger
Merger Issue Papers
Barb Naramore reported that the UMRBA is continuing to develop a series of issue papers to help guide strategic planning for merging the EMP and NESP legislative authorities. At yesterday’s EMP-CC and NECC/ECC joint meeting, new issue papers were presented on the following topics:
Martin Konrad expressed concern
at the prospect of the managing agency being responsible for O&M under
NESP. He said it is unlikely that
Roger Perk cautioned that partner unwillingness to assume O&M would be a show stopper for the Corps of Engineers. He said the Corps cannot and will not O&M ecosystem restoration projects, except where it is the managing entity. Holly Stoerker recalled that, during the evaluation of the NESP ecosystem restoration alternatives, the states specifically asked to have the O&M costs estimated because they recognized O&M as an important issue. Naramore noted that each of the states’ resource/conservation agencies provided a letter stating its support for the Feasibility Study’s proposed approach to cost sharing. In those letters, the states expressed a conceptual willingness to share some first costs under specific circumstances and to assume O&M for projects on lands they manage. While those letters did not, of course, make specific fiscal commitments, they were an important expression of the states’ general willingness to participate as cost share partners in NESP.
Janet Sternburg observed that, under the EMP, cost sharing requirements have tended to drive projects to refuge lands. Under NESP, Sternburg anticipates that cost sharing requirements will influence project design, with an effort to make projects less O&M intensive. As an example, she noted that the big wetlands management units, with their pumps and other equipment, are very expensive to maintain. Sternburg expects to see fewer such projects under NESP.
Sternburg suggested that adding NESP language to authorize funding transfers would help the Corps work with the states and other partner agencies to ensure that the necessary work can be accomplished. For example, she said state staff could conduct field surveys and similar work. However, going through a competitive bidding process is too cumbersome for such relatively small increments of work, according to Sternburg. Thus, any language that would help streamline transfers would certainly enhance program implementation.
Wooley said the Service is interested in revisiting the question of 100 percent federal funding for HREPs that benefit threatened and endangered (T&E) species. He noted that there are several potential projects on the river system that would provide significant T&E benefits. Sternburg added that, if NESP is not authorized, T&E benefits are the only hook for important projects on the Middle Mississippi, where there is little federal land.
Ken Lubinski asked what the partners envision as far as a transition process for integrating the two programs. Stoerker said the partners are currently in the midst of trying to address practical aspects of the transition, such as how the Science Panel and the SET relate, whether a particular project should be pursue under the EMP or NESP, etc. However, there is another set of legislative questions that will have to be addressed with Congress. According to Stoerker, it is those questions that the issue papers are designed to address. By stimulating discussion among the partnership, the papers are intended to inform the states’ thinking on these issues. That thinking will then form the basis of positions that the UMRBA may advocate to Congress.
Also in answer to Lubinski’s question, Hubbell said that, from an operational standpoint, the Corps is looking for opportunities for the two programs to support and learn from each other. Whatever ultimately happens with program authorization and funding, Hubbell said we will have improved our overall capability on the UMRS by seeking to integrate the EMP and NESP.
In answer to a question from Tim
Schlagenhaft, Perk said the NESP ramp-up figures presented at yesterday’s joint
meeting do not reflect any assumptions about the EMP as a separate or
integrated authority. Naramore recalled
that
Sternburg asked whether the issue papers would be modified based on input received. Stoerker said there are no immediate plans to revise the papers, explaining that they are intended to stimulate discussion. At this point, there is no particular need to try to perfect them. She went on to explain that, as the states determine what position, if any, they want to take on a particular issue, then staff will likely use the relevant issue paper as a starting place in formulating a more targeted explanation of the states’ position. Sternburg asked about the UMRBA’s timeframe in addressing the issues. Stoerker said the remaining four issues will be addressed at the May meetings. The August meeting will likely be the one at which the UMRBA then considers draft recommendations concerning the issues. However, she emphasized that it is not yet clear how this approach might mesh with the Congressional schedule. It is possible that the UMRBA may need to take some positions sooner, or that there will be no action on WRDA until after the 110th Congress convenes in January 2007.
Applying Ecosystem Goals and Objectives to the EMP
Roger Perk advocated continuing the discussion, with particular consideration of implications for the EMP — i.e., are there impediments or elements in the Science Panel’s draft goals and objectives that would require modifying the EMP’s focus? Perk said his own opinion is that there is nothing in the goals and objectives that is inconsistent with the EMP’s current focus.
Tim Schlagenhaft said there are definitely elements of the goals and objectives that cannot be addressed through the EMP. If NESP is not authorized and those aspects of the goals and objectives are important, then Schlagenhaft said the partnership should consider whether the EMP needs to be modified so that it can address those elements.
John Barko emphasized the Science Panel’s perspective that these are ecological goals and objectives for the system, not goals and objectives for any particular program. He also observed that the specific objectives are virtually guaranteed to change during the course of implementation. Given this, primary consideration at this point should be given to whether the higher level goals are acceptable.
Janet Sternburg expressed her expectation that NESP will address many of the goals and objectives, other programs will fit in where they can, and some aspects will remain unaddressed. She said the River Council will be an important mechanism for broadening collaboration on the goals and objectives. While her initial inclination was to seek elimination of some of the more far‑reaching goals and objectives, Sternburg said she is now comfortable with them as an articulation of what is needed for the system. Various programs will simply fit in where they are able and needed. Barko said Sternburg has captured the Science Panel’s intent quite well. The Panel members discussed their options extensively and ultimately concluded that they should articulate the full spectrum of ecological needs, rather than attempting to fit the goals and objectives within a particular program box.
Perk observed there is a mix of things happening right now. The project design teams (PDTs) need immediate focus. Rather than initially trying to address the full range of objectives, Perk said it would be reasonable for these groups first to focus on those objectives that can be addressed through the EMP and NESP. Work on some of the broader objectives, such as those related to water quality, could be deferred until there is a functioning River Council.
Al Fenedick observed that EPA will only actively engage in those aspects of the goals and objectives that relate to its authorities. He also stressed the need for the Corps to clarify the process for endorsing the vision, goals, and objectives and to clarify what it means for an agency or a group to make that endorsement — i.e., what expectations ensue, etc.
Bob Clevenstine urged the EMP-CC
members not to get overly focused on implementation issues related to the goals
and objectives. At this point, the focus
is simply on ratifying a working set of goals and objectives.
Chuck Theiling agreed, but stressed that the goals and objectives cannot be too malleable either. He stressed the need for continuity and predictability. Theiling also reminded the partners that no project is expected to meet all 46 objectives. Some projects will be quite narrowly targeted, while others will be broader in scope. The decision support system will be the key tool to making the goals and objectives, measures, indicators, etc. manageable when working on a particular project.
Other Business
Highlights for Staff Report to UMRBA
Holly Stoerker said the staff report to the UMRBA members would highlight the following:
Future Meetings
Barb Naramore announced that
future meetings of the EMP-CC will be held as part of the NECC/ECC, EMP-CC,
UMRBA meeting series on May 16-18, 2006 in
John Barko said the Science Panel would welcome partners’ thoughts on ecological goods and services. He suggested that this would be a good agenda topic for a joint meeting in May.
With no further business, the meeting adjourned at 3:55 p.m.
EMP-CC Attendance List
February 22, 2006
|
Charles
Barton |
|
|
Charlie
Wooley |
|
|
Mike
Jawson |
|
|
Al
Fenedick |
|
Rick Mollahan
|
Illinois
Department of Natural Resources |
Martin Konrad
|
Iowa
Department of Natural Resources |
Tim Schlagenhaft
|
Minnesota
Department of Natural Resources |
|
Janet
Sternburg |
Missouri
Department of Conservation |
Gretchen Benjamin
|
Wisconsin
Department of Natural Resources |
Rich
Worthington
|
|
|
Susan
Smith |
|
|
John
Barko |
|
Mike Thompson
|
|
Brian Markert
|
|
Kathy Kornberger
|
|
Roger Perk
|
|
Marvin Hubbell
|
|
|
Karen
Hagerty |
|
|
Chuck
Theiling |
|
|
Terry
Birkenstock |
|
|
Don
Powell |
|
|
Jeff
DeZellar |
|
|
Rebecca
Soileau |
|
|
Kevin
Bluhm |
|
|
Bill
Franz |
|
|
Larry
Shepard |
|
|
Bob
Clevenstine |
|
|
Jon
Duyvejonck |
|
|
Dick
Steinbach |
|
|
Joyce
Collins |
|
|
Karen
Westphall |
|
|
Linda
Leake |
|
|
Barry
Johnson |
|
Jennie Sauer
|
|
|
Rob
Maher |
Illinois
Department of Natural Resources |
|
Mike
Steuck |
Iowa
Department of Natural Resources |
|
Dru
Buntin |
Missouri
Department of Natural Resources |
|
Mike
Sullivan |
|
|
Catherine
McCalvin |
The
Nature Conservancy |
|
Todd
Strole |
The
Nature Conservancy |
|
Ken
Lubinski |
|
|
Mark
Beorkrem |
|
|
T.
Kevin O’Donnell |
|
|
|
|
|
|
|
|
|