Minutes of the
Upper Mississippi River System
Environmental Management Program
Coordinating Committee
February 27, 2003
Winter Quarterly Meeting
Sheraton Four Points
Charlie Wooley of
the U.S. Fish and Wildlife Service called the meeting to order at
8:03 a.m. on Thursday, February 27, 2003.
Other EMP-CC members present were Steve Cobb (USACE), Scott Stuewe
(IL DNR), Tom Boland (IA DNR), Steve Johnson (MN DNR),
Gary Christoff (MO DOC), Gretchen Benjamin (WI DNR),
and Leslie Holland-Bartels (USGS).
A complete list of attendees follows the minutes.
Minutes of the November Meeting
Steve Johnson
moved and Tom Boland seconded a motion to approve the draft minutes of the
November 20, 2002 meeting as written.
The motion carried unanimously.
[Note: Don Powell separately
indicated that construction of the Long Lake HREP should be approximately 50
percent complete by the end of 2003, not 2002, as indicated in the November
meeting minutes.]
Program Management
Roger Perk
reported that the EMP received $12.2 million under the FY 03 omnibus
appropriations measure that was signed into law on February 20. The FY 03 savings and slippage rate for the
construction general account is 18 percent, higher than anticipated. The Corps will allocate $3.501 million to
the LTRMP. This represents the standard
31.4 percent allocation, plus $509,000 from the HREP component.
Prior to passage
of the omnibus appropriations measure, the total scheduled EMP expenditures for
FY 03 were $13.2 million. Actual
expenditures through the end of December were $2.029 million. Perk noted that the EMP typically has
relatively low expenditure rates in the first two quarters of the year. He also indicated that the Corps will
actively seek overtarget funds for the EMP in FY 03, with the goal of bringing
the program’s funding level to $15 million.
Perk and Steve Cobb emphasized that competition for overtarget funding
within the Corps’ construction program will be quite high. According to Perk, the Administration’s FY
04 request for the EMP will enhance the EMP’s competitiveness in seeking
overtarget funds in FY 03. If the EMP
receives overtarget funding, the first increment will be allocated to the HREP
component in order to offset the HREP money that was redirected to the LTRMP.
Perk described
the Corps’ proposed FY 04 EMP allocations, assuming a total appropriation of
$33.32 million and a 16 percent savings and slippage rate. Using the standard 31.4/68.6 percent split, the
LTRMP and HREP components would receive $8.589 million and $18.765 million,
respectively. Administrative costs
would total $635,000, including $350,000 for the Independent Technical Review
Committee (ITRC). Holly Stoerker noted
that the President’s FY 04 EMP request is $200,000 short of full funding and
said she had assumed that the Administration was requesting less than full
funding for the ITRC. Perk said the
Corps has no basis for assigning the shortfall to any particular
component. For planning purposes, the
Corps is allocating $350,000 to the ITRC in FY 04, but this amount may change.
In implementing
the ITRC, Perk said he anticipates there will be parallels to the Navigation
Study Expert Panel. He noted that some
Expert Panel members may be candidates for the ITRC. In response to a question from Barb Naramore, Perk said the
ITRC’s parallels to the Expert Panel will be more process and structural in
nature than substantive. Perk said the
Corps will solicit input on the composition of the ITRC. Gretchen Benjamin emphasized that pulling
together a high-caliber group for the panel will take some time. She urged the Corps to consult with program
partners regarding candidates and begin recruitment efforts soon if the goal is
to convene the panel in FY 04.
Habitat Rehabilitation and Enhancement
Projects
Roger Perk
explained that the districts’ FY 03 HREP work plans are based on a $15.0
million appropriation. The Corps will
seek additional funds to permit execution at this level. However, if overtarget funding is not
secured, contract awards scheduled for later in the fiscal year will be
delayed. Perk explained that, as a
general strategy, all of the districts will accelerate project planning in FY
03, to the extent possible within available resources. The emphasis on project planning is intended
to position the program to execute an FY 04 work plan based on full
funding. The FY 04 work plans include
increased activity in all phases, including planning, design, construction, and
monitoring.
Don Powell
reported that Ambrough Slough will be MVP’s only major active construction
project in FY 03. Work is wrapping up
on Polander Lake and Trempealeau. The
district will award the construction contract on Pool 8 Islands Phase III later
in the year if funds are available.
Powell said the public is being asked to participate in a contest to
name two islands constructed as part of the Polander Lake project. He noted that the Fish and Wildlife Service
has held similar contests in the past to encourage public involvement. MVP will not be conducting any baseline or
bio-response monitoring in FY 03 due to funding constraints. However, the district will be completing six
performance evaluations and initiating seven more.
Under the
President’s budget request, MVP’s FY 04 priorities would include continued
planning on Capoli Slough and new planning starts for Conway Lake and Lake
Winnesheik. Plans call for five
projects to be in the design phase.
Construction activity would include completion of Ambrough Slough;
continuation of Pool Slough; and initiation of Spring Lake Islands, Long Meadow
Lake, and Pool 8 Islands Phase III.
Baseline and bio-response monitoring would be resumed in FY 04.
Mike Thompson
said MVS hopes to complete planning for Schenimann Chute and Stone Dike in FY
03. Planning may also be completed for
Pool 25/26. Design work will focus on
Batchtown Phase III and Calhoun Point.
Construction on Batchtown Phase II will be completed this year. If funds are available later in the year, MVS
will award construction contracts for Schenimann Chute and Calhoun Point. MVS will also allocate FY 03 resources to
evaluating the recently completed Swan Lake project.
Thompson
summarized MVS’s FY 04 work plan, which includes two or three new planning
starts on to-be-named projects, as well as planning and design work on
established projects, including Reds Landing, Establishment Chute, Salt
Lake/Ft. Chart SC, Ted Shanks, and Pool 25/26.
Thompson said the district has considerable construction capability in
Batchtown Phase III and Calhoun Point.
FY 04 evaluation priorities include completing bio-response monitoring
on Swan Lake.
Perk explained
that MVR’s FY 03 work plan includes new planning starts late in the fiscal
year. In addition, design work is
slated to begin late in the year on Rice Lake and Pool 11 Islands. FY 03 construction will include tree
planting at Gardner Division, prairie planting at Banner Marsh, completion of
the Princeton Refuge project, and work on the Pool 11 Islands project.
MVR’s FY 04
priorities include completing planning on Rice Lake, Smith’s Creek, and Pool 12
Overwintering, as well as initiating new starts. Rice Lake and Pool 12 Overwintering are scheduled to proceed
through design and reach construction in FY 04. Other projects under construction will include Gardner Division,
Lake Odessa, and Fox Island.
Long Term Resource Monitoring Program
Leslie
Holland-Bartels reported that the FY 03 LTRMP scope of work has been approved
and will be posted on UMESC’s web site within a week. She briefly highlighted several components of the FY 03 plan,
including data quality assurance, database updating, annual web reports, and
10-year discipline reports for all major monitoring components. Other efforts will include exploring options
for reducing the cost and enhancing the timeliness of land cover/land use
data. Holland-Bartels emphasized that
FY 03 tasks include a variety of analyses that will support decision-making
about the program’s future scope and composition. She noted that the quality assurance on FY 02 field data and
creation of the FY 02 annual web reports are largely complete. In addition, staff are working actively on
the 10-year discipline reports. She
noted that the switch to field computers should increase accuracy and reduce
the time needed to prepare the reports in the future. Progress is also being made on the Science Planning Process and
efforts to improve data access, including an enhanced web browser for fisheries
data and updates to the Spatial Query Tool.
There will be
limited vegetation, fish, invertebrate, and water quality sampling in FY
03. Sampling will be reduced in terms
of both frequency and spatial extent.
For example, vegetation sampling will focus on Pools 8 and 13, which are
currently showing different trends.
Additional data from these pools should help refine vegetation
models. Electrofish sampling will be
conducted in Pools 8, 13, and 26, using stratified random random sampling for
all strata. Invertebrate monitoring
will be done in Pools 8 and 13 for all strata, with 125 samples per pool. Limited water quality sampling will include
turbidity data in Pools 8 and 13 to support vegetation modeling.
According to
Holland-Bartels, the $509,000 transferred from the HREP component and $150,000
from state cooperative agreements have combined to provide the LTRMP with
FY 03 funding equivalent to what it would receive under a $15 million
appropriation and the standard LTRMP/HREP split. USGS staff have worked with the A-Team to develop a list of
overtarget priorities, should additional FY 03 funds become available. According to Holland-Bartels, there was a
general consensus among USGS staff and A-Team members that the top priority
should be restoring third period sampling to the baseline protocols. Other priorities include bathymetry and
outpool exploratory sampling.
Holland-Bartels has submitted the overtarget list to the Corps.
Gretchen
Benjamin emphasized that additional power analyses are very high on Wisconsin’s
priority list. She said the results of
such analyses will help refine monitoring and target applied research. Holland-Bartels said she also places a high
priority on power analysis, and is seeking USGS funding to help support the
work. In response to a question from Benjamin,
Holland-Bartels said the basic analyses initiated to assess program
restructuring options will be completed prior to the May EMP-CC meeting. Under the FY 03 scope of work, the 10-year
report drafts for the various monitoring components are due between April and
July, with final versions scheduled for completion prior to the end of the
fiscal year. These reports will then be
used as the basis for updating the Status and Trends Report in FY 04.
Holland-Bartels
highlighted several recent examples of analyses and projects involving LTRMP
data:
· Analysis of the fisheries component
showed that LTRMP monitoring is not capturing the main channel fish community,
but is doing an excellent job on the surrounding habitats. In addition, the analysis allowed the
elimination of some redundant gears.
· LTRMP data were used in planning the Pool
8 drawdown. The interagency planning
group anticipated that the impacts would be primarily in the lower pool, below
the Root River. But Yao Yin’s more
recent analysis of LTRMP vegetation depth data, cross-checked with bathymetry
data, suggests that the impacts of major drawdowns are more poolwide than
initially thought. The major Pool 8
drawdown in 2001 affected approximately 3,200 acres, including 500 acres above
the Root River. This is substantially
above the 2,000 acres originally predicted.
· Trend monitoring for invertebrates has
proven quite difficult because of the large proportion of “zero values.” Currently, only about 10 percent of the variability
in the data set can be explained. LTRMP
staff have learned that accounting for substrate enhances the predictive
capability of invertebrate models, explaining about 35 percent of the data
variability without increasing the number of samples.
· In order to help understand temporal
trends and predict responses to habitat change, the LTRMP must adhere to basic
statistical rules. UMESC staff are
working to develop statistically defensible models. This has proven to be particularly challenging for macroinvertebrates. However, new methods have resulted in a
mayfly model that does a much better job bringing predicted values into line
with observed data.
Tom Boland
announced that Bill Bertrand has retired from Illinois DNR and is being
replaced on the A-Team by Rob Maher.
Boland also noted that Janet Sternburg will be replacing Gary Christoff
as Missouri DOC’s A-Team representative over the next several months.
Boland described
the A-Team as enthused with the President’s FY 04 budget request, but also
concerned with the impacts that the FY 03 appropriations cut will have on the
program. Boland said the A-Team
strongly supports continuation of LTRMP analytical work, noting that the
analyses to-date have been tremendously helpful. He emphasized the need to define the baseline monitoring program,
noting that decisions about the baseline have both scientific and management
dimensions. While agreeing with
Holland-Bartels regarding the need to ask the “so what” questions, Boland said
the A-Team also strongly believes in the need to continue core data
collection. He cautioned against making
too many changes to monitoring protocols, noting that this could risk the
program’s temporal continuity. While
acknowledging the value of focused research, Boland said long term data sets
provide the critical background context.
Navigation Study
Denny Lundberg
reviewed major Navigation Study milestones, including coordination and approval
of the decision model by September 2003, identification of tentative integrated
plans with benefit-cost ratios by October 2003, public meetings in October
2003, release of the draft feasibility report in April 2004, public meetings in
May 2004, completion of the final feasibility report with an environmental
impact statement in August 2004, and release of the Chief’s Report in November
2004. Lundberg said the Corps will seek
review and input from the National Research Council at three points in this
process, including briefings this summer, after the draft feasibility report is
completed, and before the Chief’s Report is finalized. He described the plan formulation process,
which is intended to produce an integrated plan that addresses both navigation
efficiency and ecosystem restoration.
Ken Barr
described the four environmental objectives workshops that were held last
fall. According to Barr, the workshops
included a good range of agency and stakeholder participants. Participants identified both poolwide and
site-specific objectives in categories including water clarity, backwater
depth, water level, connectivity, aquatic areas, terrestrial areas, land
cover/land use, plants, fish, and birds.
Barr noted that objectives varied along the river. For example, participants from the upper
river identified a need for more isolated areas while participants on the lower
river called for increased connectivity.
Participants are currently reviewing the workshop results. Barr described next steps in the process,
including identifying management actions to meet the objectives, estimating the
costs and outcomes of various actions, analyzing environmental alternatives,
and integrating alternatives and conducting a tradeoff analysis.
Barr briefly
described the Technical Expert Review Panel, which has been convened to
identify and refine conceptual tools and models, provide guidance on developing
standardized objects, and assist in evaluating alternative ecosystem management
actions. The panel is scheduled to
complete its work in late April.
Barr summarized
the evaluation zone the Corps has proposed for the Navigation Study. The zone includes the main channel corridor
extending landward ¼ mile past the railroad grade or principal meander belt
levee, includes federal lands, and does not extend beyond the toe of
bluffs. According to Barr, this
definition encompasses a relatively small portion of the floodplain on the
lower river, but still includes the areas needed for approximately 60 to 70
percent of the environmental workshop objectives. He noted that the definition of the zone will allow for
site-specific flexibility where needed.
The Corps intends to issue a memorandum for record (MFR) in March
establishing the zone.
Joyce Collins
voiced concern with the proposed evaluation zone, noting that only a very small
portion of the Open River floodplain is included within the zone. She said the impacts of navigation system
expansion would be greatest on the lower river, while the benefits of
environmental restoration actions would be largely on the upper river under the
Corps’ approach. Barr emphasized that
the navigation project will not be the complete answer to environmental
sustainability for the system. He said
the Corps will consider targeted opportunities to address tributary impacts and
other issues that may require reaching beyond the evaluation zone, but will not
include the full width of the floodplain for the entire length of the
river. Barr also noted that the EMP
Report to Congress and LTRMP 10-year discipline reports and Status and Trends
Report will provide important input to the Navigation Study. In response to a question from Rick Nelson,
Barr encouraged comments on the evaluation zone before the Corps issues the
MFR, noting that the Corps will not be seeking comment after it is issued.
Lundberg
reported that a Pathways Group has been formed to examine sustainability
objectives for the system and identify potential pathways to
implementation. He noted that group
will involve a range of players and that its composition will be modified as
needed.
Steve Cobb asked
Barr to elaborate on the measures that will be used to evaluate the
environmental alternatives. Barr
explained that, from the list of 500 management actions, the Corps will
identify those tools that are best able to meet specific objectives, relying on
past experience to estimate cost and effectiveness. The Corps will also attempt to estimate the degree to which major
objectives will be met at given levels of investment. Barr expressed optimism that the Corps will be able to identify
where specific management actions will be most effective—e.g., where to invest
in fish passage. However, he emphasized
the importance of adaptive management and the need for appropriate
institutional arrangements and bio-response monitoring to support an adaptive
approach. Tom Edwards asked how the
Corps will involve the public in its analysis.
Barr explained that various stakeholder groups were asked to participate
in the objectives workshops last fall.
The next major opportunity for input will be October 2003, when the
Corps releases its tentative integrated plans.
Edwards asked to be included in any future solicitations for input.
Report to Congress
Roger Perk
provided a brief overview of the EMP RTC schedule. The schedule calls for finalizing draft conclusions for the report
at the May 2003 EMP-CC meeting; holding an Issue Resolution Conference, if
needed, in conjunction with the August 2003 EMP-CC meeting; holding a public
review period for the report in September 2003; and submitting the final report
to MVD in January 2004.
Role of Applied Research Relative to
Monitoring
Perk reported
that participants in the November 2002 RTC workshop advised against including
any specific recommendation regarding the role of applied research in the
LTRMP. They did, however, say that the
report should address the importance of applied research to the program. In response to a question from Steve Cobb,
Perk explained that there are no policy impediments to applied research. Rather, over the years, research has
declined as monitoring has taken an increasingly large share of the available
LTRMP funds. Cobb and the other EMP-CC
members concurred that the report should acknowledge the importance of applied
research, while being clear that no legislative or policy change is being
sought.
Coordination between the LTRMP and Other
Programs
Perk noted that
participants in the November workshop rejected several of the options outlined
in the issue paper concerning coordination between the LTRMP and other
programs. However, they requested
additional information about the information needs assessment (INA) and science
planning process. He briefly described
the information that has been provided in response to that request. Perk said he does not think a full-blown INA
is needed, advising instead to pursue the science planning process that USGS
has initiated. Steve Johnson concurred
with Perk’s recommendation.
Larry Shepard
noted that the science planning process and the INA are not equivalent, and
stressed that an INA would provide a broader look at information needs and thus
better insight into the LTRMP’s future role.
He said Congress and the public need to understand the bounds of the
program, noting that many people currently assume the LTRMP is addressing the
full range of river information needs.
Shepard said the LTRMP obviously cannot address all such needs, noting
that there are significant gaps between existing programs. He suggested that the EMP is best positioned
to identify and integrate approaches to information gathering on the UMRS. As an example, Shepard said coordination
between the LTRMP and the state water quality programs could yield significant
benefits.
Leslie
Holland-Bartels concurred with Shepard that there are important river programs
and information needs beyond the EMP.
She noted that USGS is talking with EPA about its information needs on a
separate track. However, she expressed
reservations with the prospect of an expansive INA through the EMP, emphasizing
that there are many important discussions taking place outside of EMP
circles. While the EMP should
participate in those discussions, it should not attempt to set the entire data
collection agenda for the river.
Holland-Bartels said the RTC should explicitly describe the scope of the
LTRMP and make it clear that the program is not the entire universe when it
comes to data collection on the river.
She described the science planning process as an effort to identify the
big science questions on the UMRS and break them down into discrete tasks. She distinguished these basic science
questions from information needs, characterizing information needs as more of
an end product focus.
Al Fenedick
noted that the EMP is frequently cited as a key tool for meeting environmental
objectives on the river. However, as
has been acknowledged in the Navigation Study process, adequate data are key to
an adaptive management approach to meeting those objectives. Fenedick said that an INA could help make
the necessary connections among various data collection efforts and increase
the overall efficiency of those efforts.
He urged the program partners not to lose sight of the value of an INA,
even if one is not undertaken immediately.
Holly Stoerker
observed that there seems to be an assumption that any INA would be undertaken
by the EMP. She suggested an
alternative approach, whereby the RTC could recommend a comprehensive INA for
the river, but not recommend that it be done solely by the EMP. Stoerker said such an approach might be
particularly compelling if it was also included in the Navigation Study
recommendations. Cobb concurred, noting
that the recommendation could be pursued as a Water Resources Development Act
proposal, or as a collaborative effort with resources drawn from a range of
agencies and programs. Gary Christoff
and Fenedick also expressed support for this approach. Tom Boland expressed concern with any major
undertaking at this time involving the LTRMP, noting that the program has been
through several planning and review processes and should now focus on
implementation. After further
discussion, it was agreed that Corps, USGS, EPA, and UMRBA staff will consult
further on the idea for an INA done under other auspices. The group will report back to the EMP
partners with the results of their assessment.
Funding Stability for the LTRMP
Perk described
the November workshop participants’ conclusion that the RTC should not include
recommendations related to LTRMP funding stability, unless the current LTRMP
analysis effort identifies specific measures to enhance funding stability that
require administrative or Congressional action. In response to a question from Johnson, Boland said it is very
difficult for the LTRMP to adjust its monitoring baseline downward in response
to annual funding fluctuations.
Cobb noted that
fluctuations in annual funding are difficult for both the LTRMP and HREP
components. While this is unfortunate,
Cobb stressed that any recommendation to address this through Administrative or
Congressional action would likely not be well received. He suggested that the RTC acknowledge the
challenge presented by funding fluctuations without recommending any specific
action. Barb Naramore suggested that
the challenges associated with funding fluctuations be described in a succinct
conclusion statement, rather than in a more elaborate issue discussion. She explained that a lengthy treatment of
the issue would likely be perceived as complaining. Cobb also urged care to ensure that the RTC does not
inadvertently convey the message that the partners would prefer stable funding
at a low level, rather than increased funding that may fluctuate. EMP-CC members expressed general agreement
that the RTC should include a carefully worded conclusion regarding the
importance of stable baseline funding for the EMP as a whole.
Operation and Maintenance
Perk reported
that the November workshop participants concluded the RTC should address the
Fish and Wildlife Service’s need for increased resources to operate and
maintain habitat projects on its refuges.
In addition, the workshop participants outlined several specific
considerations that should be reflected in the RTC’s discussion of the issue,
including habitat projects’ increasing pressure on the Service’s refuge O&M
budget, the Service’s essential role in the EMP, and consideration of an RTC
recommendation regarding cross-cut budgeting.
After a brief discussion, EMP-CC members concurred with the workshop
recommendations on the issue, and further agreed with the workshop participants
that broader O&M issues with implications beyond just the EMP should be
deferred for consideration through the Navigation Study.
Cost-Sharing
November
workshop participants advised that the RTC should recommend expanding the
definition of 100 percent federally funded HREPs to include those on all
federally managed and owned lands.
Currently, only those projects on national wildlife refuges are
constructed at 100 percent federal expense.
Perk also reported that the workshop participants stressed the need for
close coordination between the RTC’s cost-sharing recommendation and the
Navigation Study, which will address cost-sharing for a variety of UMR
environmental activities under different Corps authorities. Perk emphasized that the Corps may not ultimately
support a recommendation to expand the scope of 100 percent federal projects.
Gary Christoff
said Missouri would not oppose such a recommendation, but said the state will
likely work with members of its Congressional delegation to extend 100 percent
federal funding to HREPs on all publicly owned lands.
Gary Wooten
noted that lands enrolled in the Wetlands Reserve Program are federally managed
and asked whether the partners really intend to extend 100 percent federal
funding to such lands. Cobb said
extending 100 percent federal funding to lands involving easements would
present significant complications and would almost certainly be opposed by the
Corps. The EMP-CC members concluded
that the RTC should recommend 100 percent federal funding for HREPs on all
federally owned land, but not for federally managed lands that are not held in
fee title. They also agreed that the
EMP cost-sharing recommendation should be coordinated with any cost-sharing
recommendations that will be made as part of the Navigation Study.
HREP Planning and Prioritization
Perk reported
that November workshop participants concluded the RTC should not include any
specific recommendations related to HREP planning and prioritization. However, they did agree that the RTC should report
on the status and use of the habitat needs assessment and describe the HREP
planning and prioritization process developed subsequent to the 1997 RTC. Perk said the Corps has also committed to
presenting a revised planning and prioritization framework at the May EMP-CC
meeting. He explained that the revised
framework will be based on the May 2000 framework already endorsed by the
EMP-CC, but will elaborate and expand on that document as needed. EMP-CC members concurred with the approach
recommended at the November workshop and expressed interest in discussing the
revised framework at the May meeting.
EMP:
An Environmental Success Story
Perk described
the November workshop participants’ endorsement of the environmental success
story theme for the RTC. Participants
also noted that, because “success” often has the connotation of final
achievement or completion, the RTC must also emphasize that the story has not
yet ended and that more work remains to be done. Cobb said this is an extremely important theme, stressing that
the RTC must do the best possible job describing the EMP’s successes.
Wooten suggested
emphasizing environmental outcomes.
Cobb cautioned that the report must not be too dry or overly scientific
in tone. Holland-Bartels agreed, stressing
that the report should focus on the “so what”—i.e., the real world, compelling
examples of the program’s impacts. Perk
and Holland-Bartels said the Corps and USGS will request specific examples of
accomplishments and successes from the other partners. They also stressed that the RTC should not
include lengthy inventories of accomplishments, but rather should highlight
representative examples to illustrate the program’s successes.
EMP-CC members
concurred that the RTC should convey the environmental success story theme.
EMP:
Part of an Integrated Solution
Perk said the
November workshop participants agreed that the RTC should carry forward the
theme of the EMP as part of an integrated approach to meeting the UMRS’s
ecosystem needs. EMP-CC members agreed
that the RTC should present the EMP as part of an integrated solution. Bill Franz stressed that the EMP is not the
universal answer to all river problems, and observed that this theme is related
to the issue of the LTRMP’s coordination with other programs. Gretchen Benjamin expressed concern that the
EMP not take on work that should be conducted under the auspices of the
Navigation Study. Cobb emphasized that
this theme is not intended to suggest that the EMP assume the responsibilities
of other projects and programs.
Holland-Bartels said report authors should ask her directly for examples
of the LTRMP’s contribution to integrated solutions.
Caps on Delegated Approval Authority
Roger Perk said
MVD and the Districts would like to expand the Division’s approval authority
for HREPs. Currently, MVD can approve
projects under $5 million, unless there is a policy issue. Perk and Cobb proposed an RTC recommendation
to allow MVD to approve all HREPs regardless of cost, unless there is a policy
issue involved. Under this proposal,
the cap on the Districts’ approval authority would remain at $1 million. Cobb cited HREPs involving land acquisition
as an example of the type of project that would still require Washington-level
approval. Perk said he will prepare an
issue paper regarding the delegated authority issue for the EMP-CC’s
consideration at its May meeting.
Other RTC Business
Perk reported
that Corps, USGS, and UMRBA staff have been drafting the first three chapters
of the RTC. However, those drafts are
not yet ready for distribution. Perk
said he would like to refine the drafts further and distribute them for partner
review in April.
Perk said one of
the next steps in drafting the RTC will be to identify the report’s
conclusions. He noted that some of
these will come directly from the issue papers, while others will come from
other sources. As an example of a
likely conclusion, he cited the importance of the EMP to the entire river
system. Jeff Janvrin suggested a
conclusion highlighting the program’s efficiency. Cobb said this might be a possibility, but observed that it is
challenging to relate program costs to the full scope of its benefits. Benjamin recommended conclusions related to
the EMP’s value to the nation, lessons learned from the program, and the EMP’s
status as a state-of-the-art program.
Christoff advised seeking input from a wide range of program partners
and stakeholders regarding RTC conclusions.
He suggested an e-mail seeking ideas.
Holland-Bartels
urged that the RTC conclusions be well focused. She observed that many of the conclusions in the 1997 report were
rather minor and/or self-evident, detracting from the report’s major
points. Cobb recommended concentrating
the RTC’s conclusions on the program’s accomplishments. In particular, he said the report should
focus on what works, what is efficient, and what is cost-effective. Chuck Theiling cautioned that there will be
limits on the report’s ability to quantify results. Cobb said the partnership must simply characterize EMP outcomes
as best it can. Johnson noted that the
EMP has accomplished a tremendous amount, but that this is still a small part
of meeting the system’s overall ecosystem needs.
Charlie Wooley
and Don Hultman suggested testimonials from the public, stakeholders, managers,
and others to highlight the RTC’s major points. They stressed the value of putting a human face of the
program. Several EMP-CC members concurred
with this recommendation. Perk said he
will need assistance in gathering testimonials. He said he will seek assistance after he has identified the major
points he would like to highlight. Cobb
suggested that the report highlight a single project from planning to
post-construction evaluation.
Other Business
Tom Edwards described
concerns he has with an island project proposed for Peoria Lake as part of the
Illinois River Basin Restoration program.
In particular, Edwards said the project will not produce the desired
water quality benefits and will increase flood elevations. He also expressed concern that the increased
depth created by dredging will quickly be lost due to siltation. He urged a different approach, focused on
reducing sediment delivery to Peoria Lake.
Jeff Janvrin
announced availability of a report from the National Conference of State
Legislatures on land use in the Upper Mississippi River Basin.
Leslie
Holland-Bartels announced that Dave Soballe will be leaving USGS to join the
Corps’ Waterways Experiment Station.
She said USGS will soon be posting Soballe’s water quality position.
Tom Cox thanked
Perk and other Corps staff for their assistance with water level
management. He explained that
modifications to lock and dam operations saved the Service significant pumping
expenses in waterfowl management areas.
This was achieved with no adverse impact to navigation.
Barb Naramore
announced that the quarterly meeting schedule includes meetings on May 13-15,
2003 in St. Louis; August 5-7, 2003 in the Twin Cities; and November 18-20,
2003 in La Crosse. EMP-CC business
meetings will take place on the third day of each meeting cycle.
With no further
business, the meeting adjourned at 1:20 p.m.
EMP-CC
Attendance List
February 27, 2003
|
Steve Cobb |
U.S. Army
Corps of Engineers, MVD |
|
Charlie Wooley |
U.S. Fish and
Wildlife Service, Region 3 |
|
Leslie
Holland-Bartels |
U.S.
Geological Survey, UMESC |
|
Scott Stuewe |
Illinois
Department of Natural Resources |
|
Tom Boland |
Iowa
Department of Natural Resources |
|
Steve Johnson |
Minnesota Department
of Natural Resources |
|
Gary Christoff |
Missouri
Department of Conservation |
|
Gretchen
Benjamin |
Wisconsin
Department of Natural Resources |
|
Al Fenedick |
U.S.
Environmental Protection Agency, Region 5 |
|
Greg Ruff |
U.S. Army Corps
of Engineers, MVD |
|
Don Powell |
U.S. Army
Corps of Engineers, MVP |
|
Roger Perk |
U.S. Army
Corps of Engineers, MVR |
|
Ken Barr |
U.S. Army
Corps of Engineers, MVR |
|
Denny Lundberg |
U.S. Army
Corps of Engineers, MVR |
|
Darryl
Carattini |
U.S. Army
Corps of Engineers, MVR |
|
Jan Hodges |
U.S. Army
Corps of Engineers, MVR |
|
Chuck Theiling |
U.S. Army
Corps of Engineers, MVR |
|
Mark Cornish |
U.S. Army
Corps of Engineers, MVR |
|
Deb Foley |
U.S. Army
Corps of Engineers, MVS |
|
Mike Thompson |
U.S. Army
Corps of Engineers, MVS |
|
Brian Markert |
U.S. Army
Corps of Engineers, MVS |
|
Eric Laux |
U.S. Army
Corps of Engineers, MVS |
|
Tim Yager |
U.S. Fish and
Wildlife Service, Region 3 |
|
Don Hultman |
U.S. Fish and
Wildlife Service, UMR Refuge |
|
Rick Nelson |
U.S. Fish and
Wildlife Service, Rock Island Field Office |
|
Bob
Clevenstine |
U.S. Fish and
Wildlife Service, Rock Island Field Office |
|
Karen
Westphall |
U.S. Fish and
Wildlife Service |
|
Tom Cox |
U.S. Fish and Wildlife
Service, Mark Twain Complex |
|
Pam Thiel |
U.S. Fish and
Wildlife Service |
|
Joyce Collins |
U.S. Fish and
Wildlife Service |
|
Mike Steuck |
Iowa
Department of Natural Resources |
|
Janet
Sternburg |
Missouri
Department of Conservation |
|
Mike Wells |
Missouri
Department of Natural Resources |
|
Jeff Janvrin |
Wisconsin
Department of Natural Resources |
|
Gary Wooten |
Natural
Resources Conservation Service, Midwest Region |
|
Bill Franz |
U.S.
Environmental Protection Agency, Region 5 |
|
Larry Shepard |
U.S.
Environmental Protection Agency, Region 7 |
|
Tom Edwards |
River Rescue |
|
Holly Stoerker |
Upper
Mississippi River Basin Association |
|
Barb Naramore |
Upper
Mississippi River Basin Association |